(Address of principal executive office)
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F:
[   ] Form 20-F              [X] Form 40-F

DOCUMENTS INCLUDED AS PART OF THIS FORM 6-K
See the Exhibit Index hereto.
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
  B2Gold Corp.
   
Date: August 8, 2024By:/s/ Randall Chatwin
 Name:Randall Chatwin
 Title:Senior Vice President, Legal & Corporate Communications
EXHIBIT INDEX
Exhibit 
No.Description

Document









http://api.rkd.refinitiv.com/api/FilingsRetrieval3/.80161713.0001429937-24-000006b2goldlogoa.jpg.ashx

B2GOLD CORP.
Condensed Interim Consolidated Financial Statements
For the three and six months ended June 30, 2024
(Unaudited)



B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED STATEMENTS OF OPERATIONS
FOR THE THREE AND SIX MONTHS ENDED JUNE 30
(Expressed in thousands of United States dollars, except per share amounts)
(Unaudited)
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six months ended June 30, 2024For the six months ended June 30, 2023
Gold revenue$492,569 $470,854 $954,013 $944,410 
Cost of sales    
   Production costs(151,299)(152,762)(308,044)(280,366)
   Depreciation and depletion(95,008)(94,662)(185,454)(191,820)
Royalties and production taxes(33,089)(33,111)(63,116)(68,272)
Total cost of sales(279,396)(280,535)(556,614)(540,458)
Gross profit213,173 190,319 397,399 403,952 
General and administrative(12,968)(13,921)(27,106)(28,106)
Share-based payments (Note 11)
(4,792)(4,591)(9,746)(11,445)
Impairment of long-lived assets (Note 7 and Note 8)
(215,216)(4,885)(215,216)(4,885)
Gain on sale of mining interests (Note 7)
48,662 — 48,662 — 
Gain on sale of shares in associate (Note 8)
16,822 — 16,822 — 
Non-recoverable input taxes(2,695)(1,139)(6,999)(3,046)
Share of net income of associates (Note 8)
2,582 7,009 4,679 11,988 
Foreign exchange losses(11,356)(2,253)(13,735)(2,849)
Community relations(442)(1,722)(931)(2,725)
Write-down of mining interests (Note 7)
(636)— (636)(16,457)
Restructuring charges (Note 7)
 (7,080) (7,080)
Other expense
(2,322)(2,598)(7,754)(4,289)
Operating income30,812 159,139 185,439 335,058 
Interest and financing expense(7,465)(2,916)(17,036)(5,842)
Interest income7,671 6,035 13,126 11,854 
Change in fair value of gold stream (Note 14)
(8,387)(1,100)(19,239)(1,100)
Gains (losses) on dilution of associate (Note 8)
998 — (8,984)— 
Gains on derivative instruments (Note 13)
429 782 704 425 
Other income (expense)
12 (2,518)155 (4,118)
Income from operations before taxes24,070 159,422 154,165 336,277 
Current income tax, withholding and other taxes (Note 17)
(96,697)(71,205)(158,281)(147,945)
Deferred income tax recovery (Note 17)
37,850 3,633 17,820 5,422 
Net (loss) income for the period$(34,777)$91,850 $13,704 $193,754 
Attributable to:    
   Shareholders of the Company$(24,004)$80,418 $15,747 $166,391 
   Non-controlling interests (Note 12)
(10,773)11,432 (2,043)27,363 
Net (loss) income for the period$(34,777)$91,850 $13,704 $193,754 
(Loss) earnings per share (attributable to shareholders of the Company) (Note 11)
Basic$(0.02)$0.06 $0.01 $0.14 
Diluted$(0.02)$0.06 $0.01 $0.14 
Weighted average number of common shares outstanding (in thousands) (Note 11)
   Basic1,307,176 1,251,832 1,305,183 1,164,104 
   Diluted1,307,176 1,257,804 1,308,746 1,169,853 
See accompanying notes to condensed interim consolidated financial statements.

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED STATEMENTS OF COMPREHENSIVE (LOSS) INCOME
FOR THE THREE AND SIX MONTHS ENDED JUNE 30
(Expressed in thousands of United States dollars)
(Unaudited)

 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six months ended June 30, 2024For the six months ended June 30, 2023
Net (loss) income for the period$(34,777)$91,850 $13,704 $193,754 
Other comprehensive (loss) income    
Items that will not be subsequently reclassified to net income:
Unrealized (loss) gain on investments, net of deferred income tax (Note 6)
(8,162)6,621 6,809 3,045 
Other comprehensive (loss) income for the period(8,162)6,621 6,809 3,045 
Total comprehensive (loss) income for the period$(42,939)$98,471 $20,513 $196,799 
Other comprehensive (loss) income attributable to:
   Shareholders of the Company$(8,162)$6,621 $6,809 $3,045 
   Non-controlling interests —  — 
 $(8,162)$6,621 $6,809 $3,045 
Total comprehensive (loss) income attributable to:
   Shareholders of the Company$(32,166)$87,039 $22,556 $169,436 
   Non-controlling interests(10,773)11,432 (2,043)27,363 
 $(42,939)$98,471 $20,513 $196,799 

See accompanying notes to condensed interim consolidated financial statements.

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED STATEMENTS OF CASH FLOWS
FOR THE THREE AND SIX MONTHS ENDED JUNE 30
(Expressed in thousands of United States dollars)
(Unaudited)
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six months ended June 30, 2024For the six months ended June 30, 2023
Operating activities    
Net (loss) income for the period$(34,777)$91,850 $13,704 $193,754 
Mine restoration provisions settled(650)(579)(941)(579)
Non-cash charges, net (Note 18)
227,042 107,409 378,364 228,941 
Proceeds from prepaid sales (Note 15)
 — 500,023 — 
Changes in non-cash working capital (Note 18)
(79,709)15,052 (57,724)21,278 
Changes in long-term inventory(13,298)— (9,146)— 
Changes in long-term value added tax receivables(36,176)(18,749)(51,121)(44,588)
Cash provided by operating activities62,432 194,983 773,159 398,806 
Financing activities    
Repayment of revolving credit facility (Note 10)
 — (150,000)— 
Extinguishment of gold stream and construction financing
obligations (Note 14)
 (111,819) (111,819)
Repayment of equipment loan facilities (Note 10)
(3,519)(2,887)(5,906)(6,465)
Interest and commitment fees paid(1,090)(1,118)(4,669)(2,120)
Cash proceeds from stock option exercises (Note 11)
1,357 3,464 2,445 5,908 
Dividends paid (Note 11)
(45,869)(51,730)(91,858)(94,706)
Principal payments on lease arrangements (Note 10)
(1,140)(2,046)(2,588)(3,489)
Distributions to non-controlling interests (Note 12)
(2,708)(2,198)(7,288)(4,280)
Other691 770 962 1,587 
Cash used by financing activities(52,278)(167,564)(258,902)(215,384)
Investing activities    
Expenditures on mining interests:    
Fekola Mine(53,179)(74,151)(133,741)(127,946)
Masbate Mine(6,507)(6,098)(15,037)(15,051)
Otjikoto Mine(11,706)(15,630)(25,519)(32,976)
Goose Project(127,704)(68,612)(245,155)(68,612)
Fekola Regional Properties(4,924)(15,035)(9,425)(29,810)
Gramalote Project(3,560)(1,204)(6,870)(1,714)
Other exploration (Note 18)
(11,572)(24,552)(20,412)(40,543)
Cash proceeds on sale of investment in associate (Note 8)
100,302 — 100,302 — 
Cash proceeds on sale of long-term investment (Note 6)
18,661 — 18,661 — 
Purchase of long-term investment (Note 6)
(6,252)(16,764)(6,252)(31,880)
Funding of reclamation accounts(1,676)(1,351)(2,705)(2,640)
Loan to associate (Note 9)
 — (1,496)— 
Cash acquired on acquisition of Sabina Gold & Silver Corp. 38,083  38,083 
Transaction costs paid on acquisition of Sabina Gold & Silver Corp. (6,672) (6,672)
Other(295)101 (340)(3,212)
Cash used by investing activities(108,412)(191,885)(347,989)(322,973)
(Decrease) increase in cash and cash equivalents(98,258)(164,466)166,268 (139,551)
Effect of exchange rate changes on cash and cash equivalents(2,716)(3,067)(6,323)(6,188)
Cash and cash equivalents, beginning of period567,814 673,740 306,895 651,946 
Cash and cash equivalents, end of period$466,840 $506,207 $466,840 $506,207 
Supplementary cash flow information (Note 18)
See accompanying notes to condensed interim consolidated financial statements.

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED BALANCE SHEETS
(Expressed in thousands of United States dollars)
(Unaudited)
 As at June 30,
2024
As at December 31,
2023
Assets  
Current  
Cash and cash equivalents$466,840 $306,895 
Accounts receivable, prepaids and other (Note 4)
41,330 27,491 
Value-added and other tax receivables31,368 29,848 
Inventories (Note 5)
376,822 346,495 
Assets classified as held for sale (Note 7)
10,230 — 
 926,590 710,729 
Long-term investments (Note 6)
123,764 86,007 
Value-added tax receivables250,171 199,671 
Mining interests (Note 7)
3,616,534 3,563,490 
Investments in associates (Note 8)
74,193 134,092 
Long-term inventories (Note 5)
102,609 100,068 
Other assets (Note 9)
72,346 63,635 
Deferred income taxes16,645 16,927 
$5,182,852 $4,874,619 
Liabilities  
Current  
Accounts payable and accrued liabilities$178,528 $167,117 
Current income and other taxes payable113,685 120,679 
Current portion of long-term debt (Note 10)
14,857 16,256 
Current portion of mine restoration provisions2,109 3,050 
Other current liabilities7,155 6,369 
 316,334 313,471 
Long-term debt (Note 10)
25,651 175,869 
Gold stream obligation (Note 14)
158,839 139,600 
Prepaid gold sales (Note 15)
517,723 — 
Mine restoration provisions104,798 104,607 
Deferred income taxes170,004 188,106 
Employee benefits obligation21,135 19,171 
Other long-term liabilities23,777 23,820 
 1,338,261 964,644 
Equity  
Shareholders’ equity  
Share capital (Note 11)
3,485,034 3,454,811 
Contributed surplus79,721 84,970 
Accumulated other comprehensive loss(118,447)(125,256)
Retained earnings309,332 395,854 
 3,755,640 3,810,379 
Non-controlling interests (Note 12)
88,951 99,596 
 3,844,591 3,909,975 
 $5,182,852 $4,874,619 
Commitments (Note 20)
Approved by the Board"Clive T. Johnson"Director"Lisa M. Pankratz"Director

See accompanying notes to condensed interim consolidated financial statements.

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
FOR THE SIX MONTHS ENDED JUNE 30
(Expressed in thousands of United States dollars)
(Unaudited)
 2024
Shares
(‘000’s)
Share
capital
Contributed
surplus
Accumulated
other
comprehensive
loss
Retained earnings
Non-
controlling
interests
Total
equity
Balance at December 31, 20231,302,396 $3,454,811 $84,970 $(125,256)$395,854 $99,596 $3,909,975 
Net income for the period— — — — 15,747 (2,043)13,704 
Dividends (Note 11)
4,973 12,481 563 — (105,070)— (92,026)
Unrealised gain on investments, net of deferred income tax (Note 6)
— — — 6,809 — — 6,809 
Shares issued on exercise of stock options (Note 11)
1,018 2,445 — — — — 2,445 
Shares issued on vesting of RSUs
(Note 11)
1,465 6,307 (6,307)— — — — 
Shares issued on vesting of PSUs
(Note 11)
946 7,604 (7,604)— — — — 
Transactions with non-controlling interests
(Note 12)
— — — — 2,801 (8,602)(5,801)
Share-based payments (Note 11)
— — 9,485 — — — 9,485 
Transfer to share capital on exercise of stock options— 1,386 (1,386)— — — — 
Balance at June 30, 20241,310,798 $3,485,034 $79,721 $(118,447)$309,332 $88,951 $3,844,591 

 2023
Shares
(‘000’s)
Share
capital
Contributed
surplus
Accumulated
other
comprehensive
loss
Retained earnings
Non-
controlling
interests
Total
equity
Balance at December 31, 20221,074,695 $2,487,624 $78,232 $(145,869)$588,139 $103,663 $3,111,789 
Net income for the period— — — — 166,391 27,363 193,754 
Shares and replacement options issued on acquisition of Sabina Gold & Silver Corp.216,452 925,375 5,075 — — — 930,450 
Dividends (Note 11)
— — 615 — (95,486)— (94,871)
Unrealised gain on investments
— — — 3,045 — — 3,045 
Shares issued on exercise of stock options (Note 11)
2,248 5,908 — — — — 5,908 
Shares issued on vesting of RSUs
(Note 11)
1,290 5,438 (5,438)— — — — 
Shares issued on vesting of PSUs
(Note 11)
741 5,658 (8,603)— — — (2,945)
Transactions with non-controlling interests— — — — (4,779)(13,996)(18,775)
Share-based payments (Note 11)
— — 10,683 — — — 10,683 
Transfer to share capital on exercise of stock options— 2,226 (2,226)— — — — 
Balance at June 30, 20231,295,426 $3,432,229 $78,338 $(142,824)$654,265 $117,030 $4,139,038 

See accompanying notes to condensed interim consolidated financial statements.

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)

1 Nature of operations

B2Gold Corp. (“B2Gold” or the “Company”) is a Vancouver-based gold producer with three operating mines: the Fekola Mine in Mali, the Masbate Mine in the Philippines and the Otjikoto Mine in Namibia, and a fourth mine under construction, the Goose Project in Canada. The Company also owns the Gramalote Project in Colombia. The Company holds an approximately 28% interest in Versamet Royalties Corporation ("Versamet") and an approximately 25% interest in BeMetals Corp. ("BeMetals"). In addition, the Company has a portfolio of evaluation and exploration assets in a number of countries including Mali and Finland.

B2Gold is a public company which is listed on the Toronto Stock Exchange under the symbol “BTO”, the NYSE American LLC under the symbol “BTG” and the Namibian Stock Exchange under the symbol “B2G”. B2Gold’s head office is located at Suite 3400, Park Place, 666 Burrard Street, Vancouver, British Columbia, V6C 2X8.

2 Basis of preparation

These condensed interim consolidated financial statements have been prepared in accordance with International Accounting Standard 34, Interim Financial Reporting ("IAS 34"), as issued by the International Accounting Standards Board ("IASB"). These condensed interim consolidated financial statements should be read in conjunction with the audited consolidated financial statements for the year ended December 31, 2023, which have been prepared in accordance with IFRS Accounting Standards as issued by the International Accounting Standards Board ("IFRS").

These condensed interim consolidated financial statements follow the same accounting policies and methods of application as the most recent annual consolidated financial statements of the Company.

These condensed consolidated interim financial statements were authorized for issue by the Board of Directors ("Board") on August 8, 2024.

Recent IFRS pronouncements issued but not yet effective

Amendments to IFRS 9, Financial instruments, and IFRS 7, Financial instruments: Disclosures

In May 2024, the IASB issued amendments to update the classification and measurement requirements in IFRS 9 and related disclosure requirements in IFRS 7 as follows:
Clarified the recognition and derecognition date of certain financial assets and liabilities and amended the requirements related to settling financial liabilities using an electronic payment system.
Clarified how to assess the contractual cash flow characteristics of financial assets in determining whether they meet the solely payments of principal and interest criteria.
New disclosures for certain instruments with contractual terms that can change cash flows (including instruments with features linked to environmental, social and corporate governance targets).
Additional disclosure requirements for financial instruments with contingent features that do not relate directly to basic lending risks and costs.
Amended disclosures relating to equity instruments designated at fair value through other comprehensive income.

The amendments are effective for annual reporting periods beginning on or after January 1, 2026, with early application permitted for certain provisions. The Company is currently assessing the effect of these amendments to its financial statements.

IFRS 18, Presentation and disclosure in financial statements

In April 2024, the IASB issued IFRS 18, Presentation and disclosure in financial statements ("IFRS 18"), which replaces IAS 1, Presentation of financial statements. IFRS 18 introduces a specified structure for the income statement by requiring income and expenses to be presented in three defined categories (operating, investing and financing), and by specifying certain defined totals and subtotals. Where company-specific measures related to income statement disclosure are provided ("management-defined performance measures"), such as certain non-GAAP measures, IFRS 18 requires additional disclosure around those management-defined performance measures in the financial statements. IFRS 18 also provides additional guidance on principles of aggregation and disaggregation which apply to the primary financial statements and the notes. IFRS 18 does not affect the recognition and measurement of items in the financial statements, nor does it affect which items are classified in other comprehensive income and how these items are classified.

1

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
The standard is effective for reporting periods beginning on or after January 1, 2027, including for interim financial statements. Retrospective application is required and early application is permitted. The Company is currently assessing the effect of this new standard to its financial statements.

3 Significant accounting judgements and estimates

The preparation of these financial statements in conformity with IAS 34 requires judgements and estimates that affect the amounts reported. Those judgements and estimates concerning the future may differ from actual results. The following are the areas of accounting policy judgement and accounting estimates applied by management that most significantly affect the Company’s financial statements, including those areas of estimation uncertainty that could result in a material adjustment to the carrying amounts of assets and liabilities within the next financial year.

Areas of judgement

Assessment of impairment and reversal of impairment indicators for long-lived assets

The Company applies significant judgement in assessing whether there are indicators of impairment or impairment reversal present that give rise to the requirement to conduct an impairment test. Internal and external factors such as significant changes in the use of the asset, legal and permitting factors, future gold prices, operating and capital cost forecasts, quantities of mineral reserves and resources, and movements in market interest rates are used by management in determining whether there are any indicators.

During the three months ended June 30, 2024, the Company identified changes to the indicators of impairment on the Fekola Complex cash-generating unit ("CGU"), consisting of the Fekola Mine and Fekola Regional Properties. As a result, these assets were tested for impairment (Note 7).

Uncertain tax positions

The Company’s operations involve the application of complex tax regulations in multiple international jurisdictions. Determining the tax treatment of a transaction requires the Company to apply judgement in its interpretation of the applicable tax law. These positions are not final until accepted by the relevant tax authority. The tax treatment may change based on the result of assessments or audits by the tax authorities often years after the initial filing.

The Company recognizes and records potential liabilities for uncertain tax positions based on its assessment of the amount, or range of amounts of tax that will be due. The Company adjusts these accruals as new information becomes available. Due to the complexity and uncertainty associated with certain tax treatments, the ultimate resolution could result in a payment that is materially different from the Company’s current estimate of the tax liabilities.

Determination of control or significant influence over investees

The assessment of whether the Company has a significant influence or control over an investee requires the application of judgement when assessing factors that could give rise to a significant influence or control. Factors evaluated when making a judgement of control or significant influence over an investee include, but are not limited to, ownership percentage, representation on the board of directors, participation in the policy-making process, material transactions and contractual arrangements between the Company and the investee, interchange of managerial personnel, provision of essential technical information and potential voting rights. In evaluating these factors, the Company determines the level of influence over the investee the Company has. Changes in the Company's assessment of the factors used in determining if control or significant influence exists over an investee would impact the accounting treatment of the investment in the investee.

Sources of estimation uncertainty

Mineral reserve and resource estimates

Mineral reserves are estimates of the amount of ore that can be economically and legally extracted from the Company’s mining properties. The Company estimates its mineral reserves and mineral resources based on information compiled by appropriately qualified persons relating to the geological data on the size, depth and shape of the ore body, and requires complex geological judgements to interpret the data. The estimation of recoverable reserves is based upon factors such as estimates of foreign exchange rates, commodity prices, future capital requirements, metallurgical recoveries, permitting and production costs along with geological assumptions and judgements made in estimating the size, and grade of the ore body. Changes in the reserve or resource estimates may impact the carrying value of mining interests, mine restoration provisions, recognition of deferred tax assets, depreciation and amortization charges and royalties receivable.
2

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)

Impairment of long-lived assets

Long-lived assets are tested for impairment, or reversal of a previous impairment, if there is an indicator of impairment or a subsequent reversal. Calculating the estimated recoverable amount of CGUs for long-lived asset requires management to make estimates and assumptions that include such factors as mineable mineralization including reserves and resources, future production levels, operating and capital costs, application of royalty, income tax and mining tax rates, future metal prices and discount rates. Changes in any of these assumptions or estimates used in determining the recoverable amount could impact the analysis. Such changes could be material.

Fair value of financial instruments

The fair value of financial instruments that are not traded in an active market are determined using valuation techniques. In determining the fair value of the gold stream obligation (Note 14 and Note 16), the Company makes significant assumptions that are based on the underlying models and the market conditions existing at both initial recognition and the end of each reporting period.

Value-added tax receivables

The Company incurs indirect taxes, including value-added tax, on purchases of goods and services at its operating mines and development projects. Indirect tax balances are recorded at their estimated recoverable amounts within current or long-term assets, net of provisions, and reflect the Company’s best estimate of their recoverability under existing tax rules in the respective jurisdictions in which they arise. Management’s assessment of recoverability considers the probable outcomes and expected timing of claimed deductions and/or disputes. The provisions and balance sheet classifications made to date may be subject to change and such change may be material.

Long-term value-added tax receivables as at June 30, 2024 includes amounts for the Fekola Mine of $183 million (December 31, 2023 - $137 million), for the Masbate Mine of $50 million (December 31, 2023 – $45 million), and for the Gramalote Project of $17 million (December 31, 2023 - $18 million).

Current and deferred income taxes

The Company is periodically required to estimate the tax basis of assets and liabilities. Where applicable tax laws and regulations are either unclear or subject to varying interpretations, it is possible that changes in these estimates could occur that materially affect the amounts of deferred income tax assets and liabilities recorded in the financial statements. Changes in deferred tax assets and liabilities generally have a direct impact on earnings in the period that the changes occur.

Each period, the Company evaluates the likelihood of whether some portion or all of each deferred tax asset will not be realized. This evaluation is based on historic and future expected levels of taxable income and the associated repatriation of retained earnings, the pattern and timing of reversals of taxable temporary timing differences that give rise to deferred tax liabilities, and tax planning initiatives. Levels of future taxable income are affected by, among other things, metal prices, production costs, quantities of proven and probable gold reserves, interest rates and foreign currency exchange rates. The availability of retained earnings for distribution depends on future levels of taxable income as well as future reclamation expenditures, capital expenditures, dividends and other uses of available cash flow.

4 Accounts receivable, prepaids and other
 June 30, 2024December 31, 2023
 $$
Supplier advances14,977 10,533 
Prepaid expenses16,156 8,639 
Deferred transportation costs3,957 — 
Other receivables6,240 8,319 
41,330 27,491 

3

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
5 Inventories

The current inventories balance is made up as follows:
 June 30, 2024December 31, 2023
 $$
Gold and silver bullion63,134 53,065 
In-process inventory17,587 18,220 
Ore stock-pile inventory68,091 80,302 
Materials and supplies228,010 194,908 
 376,822 346,495 

The long-term inventories balance is made up as follows:
 June 30, 2024December 31, 2023
 $$
Ore stock-pile inventory63,047 56,497 
Materials and supplies39,562 43,571 
 102,609 100,068 

Current ore stock-pile inventory as at June 30, 2024 includes amounts for the Fekola Mine of $38 million (December 31, 2023 - $59 million), for the Masbate Mine of $13 million (December 31, 2023 - $14 million), for the Otjikoto Mine of $9 million (December 31, 2023 – $7 million) and for the Back River Project of $8 million (December 31, 2023 - $nil).

Long-term stock-pile inventory as at June 30, 2024 includes amounts for the Otjikoto Mine of $47 million (December 31, 2023 – $44 million), for the Fekola Mine of $8 million (December 31, 2023 - $6 million), and for the Masbate Mine of $8 million (December 31, 2023 - $6 million).

Long-term supplies inventory are supplies for the Back River Project that are expected to be either consumed in construction or beyond the next twelve months.

6 Long-term investments
 June 30, 2024December 31, 2023
Cost
$
AOCI
$
Fair Value
$
Cost
AOCI
$
Fair Value
$
Snowline Gold Corp.39,011 21,674 60,685 32,759 19,909 52,668 
Calibre Mining Corp.43,363 (1,326)42,037 — — — 
Osino Resources Corp.6,955 8,008 14,963 6,955 5,340 12,295 
St. Augustine Gold & Copper Ltd.20,193 (16,706)3,487 20,193 (15,562)4,631 
AuMEGA Metals Ltd.2,885 (980)1,905 2,885 (1,253)1,632 
RTG Mining Inc.13,400 (13,003)397 13,400 (13,092)308 
West African Resources Ltd.   20,530 (6,261)14,269 
Other899 (609)290 899 (695)204 
126,706 (2,942)123,764 97,621 (11,614)86,007 
4

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)

On June 20, 2024, the Company sold 79 million of its 111 million shares in its associate Calibre Mining Corp ("Calibre") for proceeds of $100 million (see Note 8). As a result of the decreased shareholding and no longer having the right to nominate a member to the Board of Directors of Calibre, the Company determined it no longer had significant influence over Calibre. The remaining investment of 32 million shares, valued at $43 million, was reclassified to Long-term investments in the Condensed Interim Consolidated Balance Sheet.

During the three months ended June 30, 2024, the Company sold its 22 million share investment in West African Resources Ltd. for proceeds of $19 million.

During the six months ended June 30, 2024, the Company purchased an additional 1.6 million shares of Snowline Gold Corp. ("Snowline") at an average cost of Cdn. $5.47 for a total cost of $6 million to maintain a 9.9% interest in Snowline in accordance with the Company's rights under its shareholder agreement.

7 Mining interests
 Mineral propertiesBuildings, plant & equipmentConstruction-in-progressExploration & evaluation assetsTotal
 $$$$$
Cost  
Balance at December 31, 20222,203,412 1,679,345 16,596 511,867 4,411,220 
Acquisitions 41,166 1,050,326 114,898 1,206,390 
Additions193,443 197,704 388,272 61,832 841,251 
Disposals (25,479)  (25,479)
Write-downs   (19,905)(19,905)
Transfers21,087 61,414 (61,414)(21,087) 
Change in mine restoration provision estimates(495) 363 (150)(282)
 
Balance at December 31, 20232,417,447 1,954,150 1,394,143 647,455 6,413,195 
Additions83,643 48,260 341,684 11,041 484,628 
Capitalized interest  10,399  10,399 
Disposals(21,087)(12,226)  (33,313)
Reclassified to assets held for sale   (10,230)(10,230)
Write-downs   (636)(636)
Transfers 27,376 (32,334) (4,958)
Change in mine restoration provision estimates(5,566) 3,687  (1,879)
Balance at June 30, 20242,474,437 2,017,560 1,717,579 647,630 6,857,206 
Accumulated depreciation, depletion, amortization and impairment
Balance at December 31, 2022(1,150,839)(853,167) (132,484)(2,136,490)
Depreciation and depletion(241,194)(171,155)  (412,349)
Impairment(96,800)(65,753) (154,710)(317,263)
Disposals 16,397   16,397 
Balance at December 31, 2023(1,488,833)(1,073,678) (287,194)(2,849,705)
Depreciation and depletion(96,164)(90,096)  (186,260)
Impairment(109,688)(57,855) (47,673)(215,216)
Disposals 10,509   10,509 
Balance at June 30, 2024(1,694,685)(1,211,120) (334,867)(3,240,672)
Net book value at December 31, 2023928,614 880,472 1,394,143 360,261 3,563,490 
Net book value at June 30, 2024779,752 806,440 1,717,579 312,763 3,616,534 

5

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
Impairment of the Fekola Complex CGU

During the year ended December 31, 2023, the State of Mali ("the State") introduced a new mining code (the “2023 Mining Code”) and related Local Content Law. In July 2024, the accompanying Implementation Decrees which clarify how the provisions of the 2023 Mining Code and Local Content Law should be applied were enacted into law. The Company and the State remain in ongoing negotiations related to how certain components of the 2023 Mining Code should be applied to the Fekola Complex. The final outcomes of these discussions cannot yet be determined.

For the year ended December 31, 2023, the Company recorded an impairment of $206 million for the Fekola Complex. The known and estimated changes to the financial framework of the Fekola Complex as impacted by the 2023 Mining Code and the ongoing discussions with the State are considered to be updated indicators of impairment for the Fekola Complex assets.

As a result, the Company has performed an updated impairment assessment on the Fekola Complex CGU. The carrying value of the CGU was compared to the CGU’s recoverable amount which was determined to be its fair value less costs of disposal ("FVLCD"). To estimate the recoverable amount of the CGU for impairment, the Company utilized a discounted cash flow model incorporating significant assumptions that included such factors as mineable mineralization including reserves and resources, future production levels, operating and capital costs, fuel taxes and the expected application of revised royalty and revenue based tax rates, forecast annual gold prices per ounce of $2,222 (2024), $2,231 (2025), $2,150 (2026), $2,055 (2027), long-term gold price of $1,900 per ounce thereafter, and a discount rate of 7.5% for the Fekola Complex. Management’s estimate of the FVLCD of its CGU is classified as level 3 in the fair value hierarchy. The Company’s estimate of future cash flows is subject to risks and uncertainties and therefore could change in the future if the underlying assumptions change.

The Company’s analysis concluded that the Fekola Complex CGU was impaired resulting in an impairment of $215 million. A net impairment charge of $194 million after taking into account a deferred income tax recovery of $21 million was recorded in the Condensed Interim Consolidated Statement of Operations for the six month period ended June 30, 2024.

The recoverable amount of the Fekola Complex CGU is most sensitive to changes in the gold price and discount rate. In isolation, a $50 per ounce decrease in the gold price would result in a reduction in the recoverable amount of the Fekola Complex CGU of approximately $96 million. In isolation, a 25 basis point increase in the discount rate would result in a reduction in the recoverable amount of the Fekola Complex CGU of approximately $12 million.

In addition, based on the current status of discussions with the State, the Company has recorded additional tax provisions of $37 million in the quarter ended June 30, 2024 for the expected settlement of income tax audits and assessments up to the balance sheet date (see Note 17).

Versamet transaction

On June 5, 2024, the Company entered into a purchase and sale agreement (the "Agreement") to sell a portfolio of ten metal royalties (the "Royalties") to a private company, Versamet. Under the terms of the Agreement, the royalty sale is split into two tranches.

Upon completion of the first tranche, on June 5, 2024, the Company received 122 million Versamet shares at Cdn. $0.80 per share for proceeds of $71 million in exchange for the following royalties:
2.7% net smelter return (“NSR”) royalty on the Kiaka Gold Project, with a book value of $18 million;
2.7% NSR royalty on the Toega Gold Deposit, with a book value of $3 million;
1.5% NSR royalty on the Primavera Project, with no book value; and
Two exploration stage royalties, with no book value.

6

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
The book value of the Royalties was included within mining interests. The gain on sale of mining interests on the first tranche was calculated as follows:
 $
Fair value of common shares received71,249 
Transaction costs(1,500)
Net proceeds received69,749 
Kiaka Royalty18,488 
Toega Royalty2,599 
Book value of assets sold21,087 
Gain on sale of mining interests48,662 

The Royalties comprising the second tranche are subject to certain rights of first refusal ("ROFR") that need to be exercised within 60 days of the transaction date. If these are not exercised, upon completion of the second tranche, the Company expects to receive 31 million Versamet shares at Cdn. $0.80 per share for estimated proceeds of $18 million in exchange for the following royalties:
2% NSR royalty on the Mocoa Project, with a carrying value value of $10 million;
Three additional exploration stage royalties, with a nominal carrying value.

As the sale of the Mocoa Project 2% NSR is expected to be completed within the next twelve months, its carrying value of $10 million has been classified as an asset held for sale on the Condensed Interim Consolidated Balance Sheet at June 30, 2024. The other second tranche royalties have a nominal carrying value, therefore, no adjustment is required.

The Company and Versamet also entered into an Investor Rights Agreement which entitles B2Gold to nominate one member to Versamet’s Board of Directors and pro rata participation rights with respect to future capital raises. The Company determined that it has significant influence over the decision-making processes of Versamet due to the ability to nominate a Director to the Board and owning 28% of the outstanding share capital. As a result, the Company's investment in Versamet has been recorded as an Investment in Associate in the Condensed Interim Consolidated Balance Sheet (see Note 8).

Otjikoto

During the six months ended June 30, 2023, the Company communicated to employees about the phased closure plan for the Otjikoto Mine, which subsequently commenced in 2023. The announcement of the closure plan for the mine resulted in an obligation for severance pay under Namibian law. The undiscounted severance obligation before inflation adjustments at June 30, 2023 was estimated at $9 million. The present value of these payments of $7 million was recorded as a Restructuring charge in the Condensed Interim Consolidated Statement of Operations for the six months ended June 30, 2024.

Other

During the six months ended June 30, 2024, the Company wrote-off $1 million (2023 - $16 million) relating to non-core exploration and evaluation properties that it no longer plans to proceed with.

7

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
8 Investment in associates
 CalibreVersametBeMetalsTotal
 $$$$
Cost  
Balance at December 31, 2022111,774  8,275 120,049 
Share of net income (loss)20,122  (251)19,871 
Impairment  (4,885)(4,885)
Loss on dilution(943)  (943)
 
Balance at December 31, 2023130,953  3,139 134,092 
Share of net income (loss)4,874  (195)4,679 
Loss on dilution(8,984)  (8,984)
Shares acquired 71,249  71,249 
Shares sold(83,480)  (83,480)
Transfer to long-term investments(43,363)  (43,363)
Balance at June 30, 2024 71,249 2,944 74,193 

Calibre

On January 24, 2024, the Company's associate Calibre completed the acquisition of Marathon Gold Corporation ("Marathon"). As a result of the Calibre shares issued for the acquisition of Marathon, the Company's interest in Calibre was diluted from 24% to 15%, resulting in a dilution loss of $9 million. Despite owning less than 20% of Calibre, the Company determined that it still had significant influence over its associate due to, among other things, the Company's right to nominate one Director to the Board of Calibre.

On June 20, 2024, the Company sold 79 million of its 111 million shares in Calibre for proceeds of $100 million (net of transaction costs). The gain on sale of the Calibre shares was calculated as follows:
 $
Proceeds from sale of common shares101,455 
Transaction costs(1,153)
Net proceeds received100,302 
Book value of investment in associate126,843 
Transferred to long-term investments(43,363)
Book value of assets sold83,480 
Gain on sale of investment in associate16,822 
As a result of the deceased shareholding and no longer having the right to nominate a member to the Board of Directors of Calibre, the Company determined it no longer had significant influence over Calibre. The remaining investment of 32 million shares, valued at $43 million, was reclassified to Long-term investments in the Condensed Interim Consolidated Balance Sheet (see Note 6).

Versamet transaction

On June 5, 2024, the Company closed the first tranche of sale of certain royalties to Versamet (see Note 7) in exchange for common shares in Versamet valued at $71 million. The Company and Versamet also entered into an Investor Rights Agreement which entitles B2Gold to nominate one member to Versamet’s Board of Directors and pro rata participation rights with respect to future capital raises. The Company determined that it has significant influence over the decision-making processes of Versamet due to the ability to nominate a Director to the Board and owning 28% of the outstanding share capital. As a result, the Company's investment in Versamet has been recorded as an Investment in Associate in the Condensed Interim Consolidated Balance Sheet.

8

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
BeMetals

During the six months ended June 30, 2023, the Company determined that its associate BeMetals had become impaired due to the significant and prolonged decline in the fair value of the BeMetals shares held. The Company recorded an impairment loss of $5 million to reflect the fair value of the investment in BeMetals in the Condensed Interim Consolidated Statement of Operations.

9 Other assets
 June 30, 2024December 31, 2023
 $$
Reclamation deposits52,617 50,934 
Deferred financing costs (Note 10)
5,493 — 
Restricted cash5,267 5,259 
Loan to associate7,419 5,763 
Other1,550 1,679 
 72,346 63,635 

As at June 30, 2024, reclamation deposits include amounts for the Fekola Mine of $22 million (December 31, 2023 - $21 million), for the Otjikoto Mine of $16 million (December 31, 2023 – $14 million), for the Goose Project of $11 million (December 31, 2023 - $12 million) and for the Masbate Mine of $4 million (December 31, 2023 - $4 million).

During the six months ended June 30, 2024, the Company advanced a further $2 million to its associate BeMetals.

10 Long-term debt
 June 30, 2024December 31, 2023
 $$
Revolving credit facility:
Principal amount 150,000 
Unamortized transaction costs (7,365)
 142,635 
Equipment loans and lease obligations:  
Fekola equipment loan facilities (net of unamortized transaction costs)9,538 13,875 
Goose Project equipment loan facilities (net of unamortized transaction costs)4,819 6,776 
Lease liabilities26,151 28,839 
 40,508 49,490 
Total debt40,508 192,125 
Less current portion(14,857)(16,256)
 25,651 175,869 

9

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
The changes in debt balances during the six months ended June 30, 2024 are as follows:
 Revolving credit facilityEquipment loansLease liabilitiesTotal
 $$$$
Balance at December 31, 2023142,635 20,651 28,839 192,125 
Lease liabilities incurred— — 123 123 
Debt repayments(150,000)(5,906)(2,652)(158,558)
Foreign exchange gains— (456)(812)(1,268)
Reclassification of deferred financing costs to Other Assets (Note 9)
6,637 — — 6,637 
Non-cash interest and financing expense728 68 653 1,449 
Balance at June 30, 2024— 14,357 26,151 40,508 
Current portion— (10,356)(4,501)(14,857)
— 4,001 21,650 25,651 

Revolving credit facility

The Company has a $700 million revolving credit facility ("RCF") with a syndicate of international banks. The RCF allows for an accordion feature whereby upon receipt of additional binding commitments, the facility may be further increased to $800 million any time prior to the maturity date of December 16, 2025. As at June 30, 2024, the Company had available the full undrawn capacity of $700 million. The Company has provided security on the RCF in the form of a general security interest over the Company’s assets and pledges creating a charge over the shares of certain of the Company’s direct and indirect subsidiaries. In connection with the RCF, the Company must also maintain certain ratios for leverage and interest coverage. As at June 30, 2024, the Company was in compliance with these debt covenants.

11 Share capital

The Company’s authorized share capital consists of an unlimited number of common shares and an unlimited number of preferred shares. As at June 30, 2024, the Company had 1,310,797,910 common shares outstanding (December 31, 2023 - 1,302,396,192 shares), including 1,705,000 common shares being held in trust under the Company’s Incentive Plan. No preferred shares were outstanding.

During the six months ended June 30, 2024, the Company paid two quarterly dividends of $0.04 per share each, totalling $105 million (2023 - $95 million). Of this amount, $12 million (2023 - $nil) was satisfied by the issuance of 5 million shares under the Company's Dividend Re-investment Plan.

Subsequent to June 30, 2024, on August 8, 2024, the Company approved a third quarter dividend of $0.04 payable on September 23, 2024.

During the six months ended June 30, 2024, approximately 1 million stock options were granted to employees at an exercise price of Cdn. $3.50 per share. These stock options have a term of five years and vest over a period of three years. The estimated fair value when granted of these options, totalling $0.7 million, is being recognized as a share-based payment expense over the vesting period. The fair value was calculated using the Black-Scholes option pricing model based on a risk-free annual interest rate of 3.8%, an expected life of three years, an expected volatility of 37% and a dividend yield rate of 6%.

For the six months ended June 30, 2024, share-based payments expense relating to the vesting of stock options was $1 million (2023 - $3 million). For the six months ended June 30, 2024, the Company issued 1.0 million shares for proceeds of $2 million upon the exercise of stock options. The weighted average market price of the shares at the time of exercise was Cdn. $4.02. As at June 30, 2024, 31 million stock options were outstanding.

For the three and six months ended June 30, 2024, share-based payments expense relating to the vesting of restricted share units ("RSUs") and the change in fair value of deferred share units ("DSUs") was $2 million and $4 million, respectively (2023 - $1 million and $4 million, respectively). During the six months ended June 30, 2024, the Company granted 2 million RSUs to employees and issued 1 million shares on the vesting of RSUs. As at June 30, 2024, 4 million RSUs and 2 million DSUs were outstanding.
10

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
For the three and six months ended June 30, 2024, share-based payments expense relating to the vesting of performance share units ("PSUs") was $2 million and $4 million, respectively (2023 - $2 million and $4 million, respectively). During the six months ended June 30, 2024, the Company issued 0.9 million shares on the vesting of 1.4 million PSUs.

During the six months ended June 30, 2024, the Company granted 2.6 million PSUs to employees comprised of two equal 50% tranches. Vesting of tranche one of the PSUs granted will depend on the growth of the consolidated production profile and the number of shares that may vest will be between 0% to 200% of the number of tranche one PSUs. The estimated fair value when granted of this portion of $3 million was calculated based on the fair value of the Company's stock on the date of the grant and the expected increase in the production profile. Vesting of tranche two of the PSUs granted will depend on total shareholder return of the Company compared to a group of peer companies over the period January 1, 2024 to December 31, 2026. The number of shares that may vest will be between 0% and 200% of the number of tranche two PSUs. The estimated fair value when granted of the tranche two PSUs of $3 million was calculated using a risk-neutral Monte Carlo simulation based on a correlated Geometric Brownian Motion. The model used historical share price volatility ranging from 26% to 66% for the group, a Canadian risk-free annual interest rate of 4.19%, and a United States risk-free annual interest rate of 4.52%. The fair value of both tranches is being recognized over the vesting period. As at June 30, 2024, 6 million PSUs were outstanding.

Earnings per share

The following is the calculation of basic and diluted earnings per share:
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six
months ended
June 30, 2024
For the six
months ended
June 30, 2023
Net (loss) income and diluted net (loss) income (attributable to shareholders of the Company)
$(24,004)80,418 $15,747 166,391 
Basic weighted average number of common shares outstanding (in thousands)
1,307,176 1,251,832 1,305,183 1,164,104 
Effect of dilutive securities:    
Stock options 2,033 184 1,854 
Restricted share units 725 666 681 
Performance share units 3,214 2,713 3,214 
Diluted weighted average number of common shares outstanding (in thousands)
1,307,176 1,257,804 1,308,746 1,169,853 
(Loss) earnings per share (attributable to shareholders of the Company)
Basic$(0.02)$0.06 $0.01 $0.14 
Diluted$(0.02)$0.06 $0.01 $0.14 

11

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
12 Non-controlling interests

The following is a continuity schedule of the Company's non-controlling interests:
FekolaMasbateOtjikotoOtherTotal
$$$$$
Balance at December 31, 202342,911 27,744 24,238 4,703 99,596 
Share of net (loss) income(6,356)(991)5,271 33 (2,043)
Distributions to non-controlling interest— — (6,988)— (6,988)
Interest on loan to non-controlling interest(2,380)— — — (2,380)
Participating funding from non-controlling interest— — — 638 638 
Other— — — 128 128 
Balance at June 30, 202434,175 26,753 22,521 5,502 88,951 

13 Derivative financial instruments

During the six months ended June 30, 2024, the Company entered into an additional series of forward contracts for the purchase of 27 million litres of fuel oil at an average strike price of $0.46 per litre and 41 million litres of gas oil at an average strike price of $0.62 per litre with scheduled settlement between July 2024 and April 2026. The Company's fuel derivative instruments were not designated as hedges and are being recorded at fair value through profit and loss ("FVTPL").

 202420252026Total
Forward – fuel oil:   
Litres (thousands)10,956 13,705 3,384 28,045 
Average strike price$0.47 $0.46 $0.43 $0.46 
Forward – gas oil:
Litres (thousands)12,792 22,271 5,483 40,546 
Average strike price$0.62 $0.62 $0.60 $0.62 

The unrealized fair value of these contracts at June 30, 2024 was $0.5 million (December 31, 2023 - $0.5 million).

Subsequent to June 30, 2024, the Company entered into contracts for the delivery of 31 million litres of fuel oil at a weighted average strike price of $0.43 per litre and the delivery of 7 million litres of gas oil at a weighted average strike price of $0.58 per litre.

14 Gold stream obligation

The Company's gold stream obligation requires the delivery from production at the Company's Back River Project as follows:
2.7805% of gold production up to delivery of 87,100 ounces
1.4405% of gold production up to an aggregate of 134,000 ounces
1.005% of gold production thereafter.

The gold stream obligation was determined to be a derivative liability under IFRS 9 Financial instruments, and has been classified as FVTPL. As a result, it has been recorded at its fair value on the Condensed Interim Consolidated Balance Sheet with changes in the fair value being recorded in the Condensed Interim Consolidated Statement of Operations. The fair value of the gold stream was determined to be level 3 in the fair value hierarchy (Note 16). The Company has guaranteed the gold stream obligation.

12

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
The following is a summary of the changes in the gold stream obligation:
$
Outstanding at December 31, 2023139,600
Change in fair value19,239
Outstanding at June 30, 2024158,839

On completion of the Company's acquisition of Sabina Gold & Silver Corp. ("Sabina") on April 19. 2023, the Company assumed certain construction financing and gold stream obligations from Sabina. Following completion, the Company extinguished certain gold stream and construction financing obligations for payments totalling $112 million, as follows:
a $46 million payment to extinguish one-third of the gold stream obligation;
a $63 million payment to extinguish the gold metal off take agreement;
a $2 million payment to extinguish the senior secured debt facility; and
a $1 million payment to extinguish the $75 million gold prepay facility

15 Prepaid gold sales

On January 23, 2024, the Company entered into a series of prepaid gold sales with a number of its RCF syndicate banks. Under the terms of the prepaid gold sales, the Company received an upfront payment of $500 million, based on gold forward curve prices averaging approximately $2,191 per ounce, in exchange for equal monthly deliveries of gold from July 2025 to June 2026 totaling 264,768 ounces. Gold deliveries can be from production from any of the Company’s operating mines and the prepaid gold sales can be settled prior to maturity through accelerated delivery of the remaining deliverable gold ounces.

The prepaid gold sales have been accounted in accordance with IFRS 15, Revenue from Contracts with Customers, whereby the cash prepayments have been recognized as deferred revenue on the interim condensed consolidated balance sheet and will be recognized as revenue in the interim condensed consolidated statement of operations based on the contract price when gold deliveries are made.

During the three and six months ended June 30, 2024, the Company recognized interest charge of $10 million and $18 million, respectively, relating to the financing component contained in the prepaid gold sales. The interest expense recognised in the Condensed Interim Consolidated Statement of Operations for the three and six months ended June 30, 2024 was $4 million and $9 million, respectively, net of $6 million and $9 million, respectively, capitalized to the cost of constructing qualifying assets during the period. At June 30, 2024, the carrying amount of the prepaid gold sales was $518 million.

16 Financial instruments

The Company’s financial assets and liabilities are classified based on the lowest level of input significant to the fair value measurement based on the fair value hierarchy:

Level 1 – quoted prices in active markets for identical assets or liabilities;

Level 2 – inputs other than quoted prices included in Level 1 that are observable for the asset or liability, either directly (i.e. as prices) or indirectly (i.e. derived from prices); and

Level 3 – inputs for the asset or liability that are not based on observable market data.

13

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
As at June 30, 2024, the Company’s financial assets and liabilities that are measured at fair value are categorized as follows:
 As at June 30, 2024As at December 31, 2023
 Level 1Level 2Level 3Level 1Level 2Level 3
 $$$$$$
Long-term investments (Note 6)
123,764   86,007   
Fuel derivative contracts (Note 13)
 482   481  
Gold stream obligation (Note 14)
  (158,839)  (139,600)

The Company’s long-term investments consist of shares of publicly traded mining companies. The fair values of these were determined using market quotes from an active market for each investment.

The fair value of the Company's fuel derivative contracts were determined using prevailing market rates for instruments with similar characteristics.

The fair value of the gold stream was calculated based on an income approach and a discounted cash flow model. The calculated fair value includes inputs that are based on observable market data, including forward gold price curves and credit adjusted risk-free rates. The fair value also includes inputs that are not based on observable market data, including the timing of future gold deliveries. The valuation has been prepared by an independent valuations specialist with direct oversight from the Company. Gold production is assumed to begin at the end of the second quarter of 2025. Forward gold price estimates ranged from $2,331 to $2,706 per ounce. A $100 per ounce change in the gold forward price would have approximately a $6 million impact on the fair value of the gold stream obligation. A 50 basis point change in the risk-free rate would also have approximately a $6 million impact on the fair value of the gold stream obligation.

The fair value of the Company's long-term debt also approximates its carrying value as it has a floating interest rate and the Company's credit spread has remained approximately consistent. The fair value of the Company's other financial instruments approximate their carrying value due to their short-term nature.

Credit risk

The Company’s maximum exposure to credit risk was the book value of cash and cash equivalents, accounts receivable, loans receivable and the carrying value of its derivative portfolio. The Company limits its credit exposure on cash and cash equivalents by holding its deposits mainly with high credit quality financial institutions as determined by credit rating agencies. The Company maintains its excess cash balances in short-term investments accounts. The Company does not maintain insurance for its cash balances.

14

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
17 Income and other taxes

Income tax expense differs from the amount that would result from applying the Canadian federal and provincial income tax rates to earnings from operations before taxes. These differences result from the following items:
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six
months ended
June 30, 2024
For the six
months ended
June 30, 2023
 $$$$
Income from operations before taxes24,070 159,422 154,165 336,277 
Canadian federal and provincial income tax rates27.00 %27.00 %27.00 %27.00 %
Income tax expense at statutory rates6,499 43,044 41,625 90,795 
Increase (decrease) attributable to:    
Benefit not recorded on impairment losses48,985 — 48,985 — 
Change in accruals for tax audits37,135 1,506 37,135 1,506 
Future withholding tax(19,344)(800)(4,524)5,600 
Effects of different foreign statutory tax rates(5,715)8,559 4,646 20,525 
Change due to foreign exchange5,931 (4,358)13,239 (8,149)
Benefit of optional tax incentives(5,235)(4,564)(9,046)(6,229)
Change in non-taxable portion of gains(9,325)582 (8,261)(90)
Non-deductible expenditures1,615 3,862 8,189 11,098 
Withholding and other taxes1,883 10,488 4,827 12,264 
Change in losses and tax bases for which no tax benefit has been recorded(2,545)11,149 3,753 15,506 
Use of losses and temporary differences not previously recognised(1,351)— (1,351)— 
Amounts under (over) provided in prior years314 (1,896)1,244 (303)
Income tax expense58,847 67,572 140,461 142,523 
Current income tax, withholding and other taxes96,697 71,205 158,281 147,945 
Deferred income tax recovery(37,850)(3,633)(17,820)(5,422)
Income tax expense58,847 67,572 140,461 142,523 

Included in current income tax expense for the three and six months ended June 30, 2024 was $5 million and $13 million, respectively (2023 - $10 million and $19 million, respectively), related to the State of Mali's 10% priority dividend on its free carried interest in the Fekola Mine. This priority dividend is accounted for as an income tax in accordance with IAS 12, Income Taxes.

Based on the current status of discussions with the State, the Company has recorded additional tax provisions of $37 million in the quarter ended June 30, 2024 for the expected settlement of income tax audits and assessments up to the balance sheet date (see Note 7).

Pillar Two Global Minimum Tax

In June 2024, Canada enacted the Global Minimum Tax Act that was developed within the framework of the OECD’s Pillar Two global minimum tax regime, effective January 1, 2024. As Pillar Two legislation has been enacted or substantively enacted in certain jurisdictions in which the Company operates, the legislation is effective for the Company's financial year beginning January 1, 2024.

The Company has performed an assessment of its potential exposure to Pillar Two income taxes. This assessment is based on the most recent information available regarding the financial performance of the constituent entities of the consolidated group. Based on the assessment performed, the Company does not expect any material exposure to Pillar Two top-up taxes.

15

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
18 Supplementary cash flow information

Supplementary disclosure of cash flow information is provided in the tables below:

Non-cash charges (credits):
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six
months ended
June 30, 2024
For the six
months ended
June 30, 2023
 $$$$
Depreciation and depletion95,008 94,662 185,454 191,820 
Gain on sale of mining interests (Note 7)
(48,662)— (48,662)— 
Deferred income tax recovery (Note 17)
(37,850)(3,633)(17,820)(5,422)
Change in fair value of gold stream (Note 14)
8,387 1,100 19,239 1,100 
Non-cash interest and financing expense7,465 2,916 17,036 5,842 
Gain on sale of shares in associate (Note 8)
(16,822)— (16,822)— 
Share-based payments (Note 11)
4,619 3,398 9,498 10,252 
Dilution loss on associate (Note 8)
(998)— 8,984 — 
Non-recoverable input taxes2,695 296 6,581 2,203 
Share of net income of associate (Note 8)
(2,582)(7,009)(4,679)(11,988)
Write-down of mining interests (Note 7)
636 — 636 16,457 
Unrealized (gains) losses on derivative instruments(119)757 (1)3,545 
Restructuring charges (Note 7)
 7,080  7,080 
Impairment of long-lived assets (Note 7 and Note 8)
215,216 4,885 215,216 4,885 
Other49 2,957 3,704 3,167 
 227,042 107,409 378,364 228,941 

Changes in non-cash working capital:
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six
months ended
June 30, 2024
For the six
months ended
June 30, 2023
 $$$$
Accounts receivable and prepaids(15,747)734 (14,198)(5,871)
Value-added and other tax receivables(2,322)1,981 (7,438)1,336 
Inventories(35,389)10,336 (35,186)(12,331)
Accounts payable and accrued liabilities(7,518)(3,440)6,092 (8,410)
Current income and other taxes payable(18,733)5,441 (6,994)46,554 
 (79,709)15,052 (57,724)21,278 

16

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
Other exploration and development:
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six
months ended
June 30, 2024
For the six
months ended
June 30, 2023
 $$$$
Fekola Mine, exploration(838)— (2,140)(1,706)
Masbate Mine, exploration(928)(1,008)(1,749)(1,967)
Otjikoto Mine, exploration(1,514)(996)(3,303)(1,490)
Goose Project, exploration(7,038)(2,048)(9,350)(2,048)
Finland Properties, exploration(715)(1,721)(2,108)(3,992)
Bakolobi Property, exploration (2,088)(344)(3,268)
Menankoto Property, exploration (7,593) (10,629)
Bantako North Property, exploration (3,782) (5,223)
Dandoko Property, exploration (3,154)20 (6,627)
George Property, exploration (1,277)(157)(1,277)
Other(539)(885)(1,281)(2,316)
(11,572)(24,552)(20,412)(40,543)

Non-cash investing and financing activities:
 For the three
months ended
June 30, 2024
For the three
months ended
June 30, 2023
For the six
months ended
June 30, 2024
For the six
months ended
June 30, 2023
 $$$$
Share consideration received on sale of mining interests (Note 7)
71,249 — 71,249 — 
Interest capitalized to construction of qualifying assets6,843 — 10,399 — 
Interest on loan to non-controlling interest1,400 1,224 2,801 2,397 
Change in current liabilities relating to mining interest expenditures8,554 6,824 4,800 5,592 
Foreign exchange loss on Fekola equipment loan facility(685)(131)(400)(375)
Change in accrued distributions to non-controlling interest 9,967 (300)9,967 
Share-based payments, capitalized to mining interests53 160 234 278 
Common shares issued on acquisition of Sabina Gold & Silver Corp. 925,375  925,375 
Fair value of B2Gold replacement options on acquisition of Sabina Gold & Silver Corp. 5,075  5,075 

For the three and six months ended June 30, 2024, the Company paid $133 million and $172 million, respectively, of current income tax, withholding and other taxes in cash (2023 - $59 million and $90 million, respectively).

19 Segmented information

The Company’s reportable operating segments include its mining operations and development projects, namely the Fekola, Masbate and Otjikoto mines and the Goose Project. It also includes Fekola Regional properties, which are in the exploration and evaluations stage. The Fekola Regional segment includes the Bantako North, Menankoto, Dandoko and Bakolobi properties. The “Other Mineral Properties” segment consists of the Company’s interests in mineral properties which are at various stages of exploration and evaluation, including the Company's interest in the Gramalote Project, as well as the Company's equity accounted investment in its associates Versamet and BeMetals. The “Corporate and Other” segment includes corporate operations.

17

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
The Company’s segments are summarized in the following tables:
For the three months ended June 30, 2024
Fekola
Mine
Fekola RegionalMasbate
Mine
Otjikoto
Mine
Goose ProjectOther
Mineral
Properties
Corporate
& Other
Total
$$$$$$$$
External gold revenue270,592 — 109,083 112,894 — — — 492,569 
Production costs81,481 — 37,602 32,216 — — — 151,299 
Depreciation & depletion42,469 461 19,811 32,267 — — 539 95,547 
Impairment of long-lived assets162,673 52,543 — — — — — 215,216 
Net (loss) income(82,289)(48,430)24,946 25,187 (1,085)961 45,933 (34,777)
Capital expenditures54,017 4,923 7,435 13,220 134,742 4,820 566 219,723 
Total assets1,311,340 170,573 726,356 390,894 1,787,693 309,957 486,039 5,182,852 
For the three months ended June 30, 2023
Fekola
Mine
Fekola RegionalMasbate
Mine
Otjikoto
Mine
Goose ProjectOther
Mineral
Properties
Corporate
& Other
Total
$$$$$$$$
External gold revenue281,672 — 111,291 77,891 — — — 470,854 
Production costs79,245 — 48,170 25,347 — — — 152,762 
Depreciation & depletion50,367 — 23,336 20,929 — — 518 95,150 
Impairment of long-lived assets— — — — — 4,885 — 4,885 
Net income (loss)76,495 (384)16,161 9,125 (2,919)7,135 (13,763)91,850 
Capital expenditures74,151 31,653 7,106 16,626 70,660 5,086 63 205,345 
Total assets1,573,172 263,843 746,005 432,469 1,190,683 436,450 288,263 4,930,885 
For the six months ended June 30, 2024
Fekola
Mine
Fekola RegionalMasbate
Mine
Otjikoto
Mine
Goose ProjectOther
Mineral
Properties
Corporate
& Other
Total
$$$$$$$$
External gold revenue526,910 — 208,050 219,053 — — — 954,013 
Production costs166,586 — 80,373 61,085 — — — 308,044 
Depreciation & depletion87,809 1,622 38,999 57,024 — — 1,036 186,490 
Impairment of long-lived assets162,673 52,543 — — — — — 215,216 
Net (loss) income(40,190)(51,061)41,217 51,346 (1,777)2,723 11,446 13,704 
Capital expenditures135,881 9,749 16,786 28,822 254,505 10,421 615 456,779 
Total assets1,311,340 170,573 726,356 390,894 1,787,693 309,957 486,039 5,182,852 
18

B2GOLD CORP.
NOTES TO THE CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS
For the six months ended June 30, 2024
(All tabular amounts are in thousands of United States dollars unless otherwise stated)
(Unaudited)
For the six months ended June 30, 2023
Fekola
Mine
Fekola RegionalMasbate
Mine
Otjikoto
Mine
Goose ProjectOther
Mineral
Properties
Corporate
& Other
Total
$$$$$$$$
External gold revenue595,897 — 168,283 180,230 — — — 944,410 
Production costs156,906 — 73,163 50,297 — — — 280,366 
Depreciation & depletion105,599 — 35,695 50,526 — — 979 192,799 
Impairment of long-lived assets— — — — — 4,885 — 4,885 
Net income (loss)171,748 (515)24,961 33,544 (2,919)(2,057)(31,008)193,754 
Capital expenditures129,652 55,558 17,018 34,466 70,660 9,298 158 316,810 
Total assets1,573,172 263,843 746,005 432,469 1,190,683 436,450 288,263 4,930,885 
The Company’s mining interests are located in the following geographical locations:
June 30, 2024December 31, 2023
$$
Mining interests
Canada1,784,638 1,509,289 
Mali984,875 1,131,343 
Philippines509,510 533,781 
Namibia235,089 264,747 
Colombia62,756 66,184 
Finland35,061 32,954 
Burkina Faso 21,087 
Other4,605 4,105 
 3,616,534 3,563,490 

20 Commitments

As at June 30, 2024, the Company had the following commitments (in addition to those disclosed elsewhere in these financial statements):
For payments at the Fekola Mine of $17 million related to underground development, $13 million related to mobile purchases and rebuilds, $6 million related to the solar plant expansion, $3 million related to the construction of a new tailing storage facility, and $2 million related to plant and powerhouse maintenance. Of these amounts, $37 million is expected to be incurred in 2024 and the remaining $4 million in 2025.
For payments at the Goose Project of $43 million related to construction activities and $1 million related to mobile equipment, all of which is expected to be incurred in 2024.
For payments at the Masbate Mine of $1 million related to process plant equipment, all of which is expected to be incurred in 2024.

19
Document



B2GOLD CORP.
MANAGEMENT’S DISCUSSION AND ANALYSIS
For the quarter ended June 30, 2024

This Management’s Discussion and Analysis (“MD&A”) has been prepared as at August 8, 2024 and contains certain "forward-looking information" and “forward-looking statements” under Canadian and United States securities laws, respectively ("forward-looking statements"). All statements included herein, other than statements of historical fact, including without limitation statements regarding potential mineralization, exploration results and future plans, production and objectives of B2Gold Corp. (the “Company” or “B2Gold”), are forward-looking statements that involve various risks, uncertainties and assumptions. See the “Cautionary Statement on Forward-Looking Information” section. There can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements as a result of a number of factors, including those set out in “Risks and Uncertainties.”
The following discussion of the operating results and financial position of the Company should be read in conjunction with the unaudited condensed interim consolidated financial statements and the notes thereto of the Company for the three and six months ended June 30, 2024 and the annual consolidated financial statements and the notes thereto of the Company for the year ended December 31, 2023. The unaudited condensed interim consolidated financial statements have been prepared in accordance with IAS 34, Interim Financial Reporting, as issued by the International Accounting Standards Board ("IAS 34"). The unaudited condensed interim financial statements should be read in conjunction with the annual consolidated financial statements for the year ended December 31, 2023, which have been prepared in accordance with IFRS Accounting Standards as issued by the International Accounting Standards Board ("IFRS"). All amounts are expressed in United States dollars, unless otherwise stated. All production results and the Company's guidance presented in this MD&A reflect total production at the mines the Company operates on a 100% basis. Production from the La Libertad, El Limon and Pan mines owned by Calibre Mining Corp. ("Calibre") is presented on an approximate 24% basis until January 24, 2024 and 14% subsequently until June 20, 2024 (second quarter of 2023 - 24%), representing the Company’s indirect ownership interest in Calibre's operations through its equity investment in Calibre. On June 20, 2024, the Company sold 79 million common shares of Calibre reducing its ownership interest to approximately 4% resulting in the Company determining that it no longer has significant influence over Calibre. As a result, subsequent to June 20, 2024, the Company no longer records attributable production representing the Company’s indirect ownership interest in the mines owned by Calibre through an equity investment.

Additional information related to B2Gold, including our Annual Information Form, is available on the Company's website www.b2gold.com and on SEDAR+ at www.sedarplus.ca.

INDEX
Overview
Review of Financial Results
Review of Mining Operations and Development Projects
Liquidity and Capital Resources
Critical Accounting Estimates
Risks and Uncertainties
Internal Control Over Financial Reporting
Non-IFRS Measures
Summary of Quarterly Results
Summary and Outlook
Outstanding Share Data
Cautionary Statement on Forward-Looking Information

1



OVERVIEW
B2Gold is a Vancouver-based gold producer with three operating mines: the Fekola Mine in Mali, the Masbate Mine in the Philippines and the Otjikoto Mine in Namibia, and a fourth mine under construction in Canada, the Goose Project. The Company holds an approximately 28% interest in Versamet Royalties Corporation ("Versamet") and an approximately 25% interest in BeMetals Corp. ("BeMetals"). In addition, the Company has a portfolio of exploration and development projects in a number of countries including Mali, Finland and Colombia.
Summary
Consolidated gold revenue for the second quarter of 2024 was $493 million on sales of 210,228 ounces at an average price of $2,343 per ounce compared to $471 million on sales of 239,100 ounces at an average price of $1,969 per ounce in the second quarter of 2023. The increase in gold revenue of 5% ($22 million) was attributable to a 19% increase in average realized gold price partially offset by a 12% decrease in gold ounces sold. Consolidated gold revenue for the first half of 2024 was $954 million on sales of 433,206 ounces at an average price of $2,202 per ounce compared to $944 million on sales of 488,250 ounces at an average price of $1,934 per ounce in the first half of 2023. The increase in gold revenue of 1% ($10 million) was attributable to a 14% increase in average realized gold price partially offset by 11% decrease in gold ounces sold.
For the second quarter of 2024, total gold production was 212,508 ounces (including 8,267 ounces of attributable production from Calibre), 4% (9,493 ounces) lower than budget, and lower than the second quarter of 2023 by 19% (50,193 ounces). Consolidated gold production from the Company’s three operating mines was 204,241 ounces in the second quarter of 2024, 3% (6,979 ounces) lower than budget, and 17% (41,720 ounces) lower compared to the second quarter of 2023. For the second quarter of 2024, production from the Masbate and Otjikoto mines was 2% (914 ounces) and 4% (1,643 ounces) higher than budget, respectively, while the Fekola Mine production was 8% (9,536 ounces) lower than budget as a result of equipment availability issues (refer to "Review of Mining Operations and Development Projects" section below). In the second quarter of 2024, the Otjikoto Mine produced 9% (4,087 ounces) more ounces than the second quarter of 2023, while the Fekola and Masbate mines produced 27% (40,844 ounces) and 10% (4,963 ounces) less ounces, respectively, compared to the second quarter of 2023. For the first half of 2024, total gold production was 438,224 ounces (including 19,644 ounces of attributable production from Calibre), 1% (5,271 ounces) lower than budget, and 17% (91,333 ounces) lower compared to the first half of 2023. Consolidated gold production from the Company’s three operating mines was 418,580 ounces in the first half of 2024, 1% (3,353 ounces) lower than budget and 16% (78,100 ounces) lower compared to the first half of 2023. For the first half of 2024, production from the Masbate and Otjikoto mines was 3% (3,141 ounces) and 4% (3,559 ounces) higher than budget, respectively, while the Fekola Mine production was 4% (10,053 ounces) lower than budget. In the first half of 2024, the Otjikoto Mine produced 13% (11,012 ounces) more ounces than the first half of 2023, while the Fekola and Masbate mines produced 28% (87,567 ounces) and 2% (1,545 ounces) less ounces, respectively, compared to the first half of 2023.
For the second quarter of 2024, consolidated cash operating costs1 were $808 per gold ounce produced ($720 per gold ounce sold), $57 (7%) lower than budget and $201 (33%) per gold ounce produced higher than the second quarter of 2023. Including estimated attributable results for Calibre, cash operating costs for the second quarter of 2024 were $839 per gold ounce produced ($753 per gold ounce sold), $35 (4%) lower than budget and $203 (32%) per gold ounce produced higher than the second quarter of 2023. For the first half of 2024, consolidated cash operating costs were $762 per gold ounce produced ($711 per gold ounce sold), $74 (9%) lower than budget and $171 (29%) per gold ounce produced higher than the first half of 2023. Including estimated attributable results for Calibre, cash operating costs for the first half of 2024 were $785 per gold ounce produced ($736 per gold ounce sold), $61 (7%) lower than budget and $167 (27%) per gold ounce produced higher than the first half of 2023. Cash operating costs per ounce produced for the second quarter of 2024 and first half of 2024 were lower than budget largely as a result of lower than budgeted fuel costs, lower tonnage mined at the Fekola Mine due to equipment availability and lower deferred stripping and underground development costs at the Otjikoto Mine. Compared to the second quarter of 2023 and the first half of 2023, cash operating costs per ounce produced for the second quarter of 2024 and first half of 2024 were higher mainly due to higher ounces produced in the second quarter and first half of 2023.

1 “Cash operating costs” a non-IFRS measure; for a description of how we calculate this measure and a reconciliation from this measure to the most directly comparable measure specified, defined or determined under IFRS and presented in our financial statements, refer to “Non-IFRS Measures”
2



Consolidated all-in sustaining costs2 for the second quarter of 2024 were $1,244 per gold ounce sold compared to budget of $1,412 per gold ounce sold and $1,210 per gold ounce sold for the second quarter of 2023. Including estimated attributable results for Calibre, all-in sustaining costs for the second quarter of 2024 were $1,267 per gold ounce sold compared to budget of $1,408 per gold ounce sold and $1,214 per gold ounce sold for the second quarter of 2023. All-in sustaining costs for the second quarter of 2024 were $141 (10%) per gold ounce sold lower than budgeted due to lower than budgeted production costs per gold ounce sold and lower than budgeted sustaining capital expenditures, partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures were mainly a result of timing of expenditures and are expected to be incurred later in 2024. Consolidated all-in sustaining costs for the first half of 2024 were $1,296 per gold ounce sold compared to budget of $1,472 per gold ounce sold and $1,128 per gold ounce sold for the first half of 2023. Including estimated attributable results for Calibre, all-in sustaining costs for the first half of 2024 were $1,308 per gold ounce sold compared to budget of $1,465 per gold ounce sold and $1,135 per gold ounce sold for the first half of 2023. Consolidated all-in sustaining costs for the first half of 2024 were $157 (11%) per gold ounce sold lower than budgeted due to lower than budgeted production costs per gold ounce sold, higher gold ounces sold and lower than budgeted sustaining capital expenditures, partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures were mainly a result of timing of expenditures and are expected to be incurred later in 2024.

Total gold production for 2024 is expected to be impacted by the delay in mining higher grade material from Phase 7 of the Fekola pit due to equipment availability issues. In addition, following the sale of a portion of the Company's equity interest in Calibre in June 2024, the Company will stop reporting its share of attributable Calibre production going forward. In 2024, B2Gold now expects total gold production to be between 800,000 and 870,000 ounces (including 20,000 ounces of attributable production from Calibre) (original guidance range of between 860,000 and 940,000 ounces). The expected decrease in gold production relative to 2023 was also attributable to lower production at the Fekola Complex as a result of the delay in receiving an exploitation license for Fekola Regional from the Government of Mali, delaying the 80,000 to 100,000 ounces that were scheduled in the life of mine plan to be trucked to the Fekola mill and processed in 2024 but now expected to commence in 2025. The Company’s total consolidated cash operating costs for the year (including estimated attributable results for Calibre) are forecast to be between $835 and $895 per ounce and total consolidated all-in sustaining costs (including estimated attributable results for Calibre) are now forecast to be between $1,420 and $1,480 per ounce (original guidance range of between $1,360 and $1,420 per ounce). The anticipated increase in the Company's consolidated cash operating costs per ounce for 2024 reflects the processing of lower-grade ore at Fekola in 2024. The total consolidated all-in sustaining costs per ounce for 2024 reflect the final full year of spending on both the new Fekola Tailings Storage Facility ("TSF") and the Fekola solar plant expansion, in addition to the ongoing substantial capitalized stripping campaign planned at Fekola for 2024.

For the second quarter of 2024, the Company generated a net loss of $35 million compared to a net income of $92 million in the second quarter of 2023, including a net loss attributable to the shareholders of the Company of $24 million (net loss attributable to shareholders of the Company of $0.02 per share) in the second quarter of 2024 compared to a net income attributable to the shareholders of the Company of $80 million ($0.06 per share) in the second quarter of 2023. Adjusted net income attributable to the shareholders of the Company3 for the second quarter of 2024 was $78 million ($0.06 per share) compared to adjusted net income of $86 million ($0.07 per share) in the second quarter of 2023. For the first half of 2024, the Company generated net income of $14 million compared to a net income of $194 million in the first half of 2023, including net income attributable to the shareholders of the Company of $16 million ($0.01 per share) in the first half of 2024 compared to $166 million ($0.14 per share) in the first half of 2023. Adjusted net income attributable to the shareholders of the Company for the first half of 2024 was $160 million ($0.12 per share) compared to adjusted net income attributable to the shareholders of the Company of $192 million ($0.16 per share) in the first half of 2023.

Cash flow provided by operating activities was $62 million in the second quarter of 2024 compared to $195 million in the second quarter of 2023, a decrease of $133 million due mainly to higher working capital outflows, higher long-term value added tax receivables outflows and higher long-term inventory outflows, partially offset by higher revenues. Cash income and withholding tax payments in the second quarter of 2024 totalled $133 million (second quarter of 2023 - $59 million), including approximately $82 million related to 2023 outstanding tax liability obligations. Cash flow provided by operating activities was $773 million in the first half of 2024 compared to $399 million in the first half of 2023, an increase of $374 million due mainly to $500 million of proceeds received from the Gold Prepay in January 2024, higher revenues, partially offset by higher production costs, higher working capital outflows and higher long-term inventory outflows. Cash income and withholding tax payments in the first half of 2024 totalled $172 million (first half of 2023 - $90 million), including approximately $88 million related to 2023 outstanding tax liability obligations. Based on actual results for the first quarter of 2024 and revised forecast assumptions, including an average forecast gold price of $2,150 per ounce for the balance of 2024 (previously $2,000 per ounce), the Company is now forecasting to make total cash income tax payments for current income tax, withholding and other taxes in 2024 of approximately $289 million (previous estimate was $270 million).

2 “All-in sustaining costs” is a non-IFRS measure; for a description of how we calculate this measure and a reconciliation from this measure to the most directly comparable measure specified, defined or determined under IFRS and presented in our financial statements, refer to “Non-IFRS Measures”
3 Adjusted net income attributable to shareholders of the Company” is a non-IFRS measure; for a description of how we calculate this measure and a reconciliation from this measure to the most directly comparable measure specified, defined or determined under IFRS and presented in our financial statements, refer to “Non-IFRS Measures”
3



B2Gold continues to maintain a strong financial position and liquidity. At June 30, 2024, the Company had cash and cash equivalents of $467 million (December 31, 2023 - $307 million) and working capital (defined as current assets less assets classified as held for sale and current liabilities) of $600 million (December 31, 2023 - $397 million). At June 30, 2024, the full amount of the Company's $700 million revolving credit facility ("RCF") was undrawn and available.

In January 2024, to further enhance the financial flexibility of the Company and provide additional cash liquidity as the Company continues to fund sustaining, development and growth projects across the operating portfolio, and increase financial capacity for potential growth projects in Namibia and Colombia, B2Gold entered into a series of prepaid gold sales (the "Gold Prepay") with a number of its existing RCF syndicate lenders. The Company received an upfront payment of $500 million, based on gold forward curve prices averaging approximately $2,191 per ounce, in exchange for equal monthly deliveries of gold from July 2025 to June 2026 totaling 264,768 ounces, representing approximately 12% of expected annual gold production in each of 2025 and 2026 (subject to finalization of production guidance for 2025 and 2026). Gold deliveries can be from production from any of the Company’s operating mines and the Gold Prepay can be settled prior to maturity through accelerated delivery of the remaining deliverable gold ounces. The Gold Prepay was executed by Bank of Montreal, Canadian Imperial Bank of Commerce, ING Capital Markets LLC, and National Bank of Canada.

In the first half of 2024, B2Gold’s Board of Directors ("Board") declared two quarterly cash dividends for the first and second quarters of 2024 of $0.04 per common share each (or an expected $0.16 per share on an annualized basis). The declaration and payment of future quarterly dividends remains at the discretion of the Board and will depend on the Company's financial results, cash requirements, future prospects and other factors deemed relevant by the Board.

On January 31, 2024, the Company announced positive exploration drilling results from the Antelope deposit at the Otjikoto Mine. The Antelope deposit, which comprises the Springbok Zone, the Oryx Zone, and a possible third structure, Impala, subject to further confirmatory drilling, is located approximately 3 kilometres ("km") south of the Otjikoto open pit. On June 20, 2024, the Company announced an initial Inferred Mineral Resource estimate for the Springbok Zone, the southernmost shoot of the recently discovered Antelope deposit. Over 36,000 metres have been drilled into the Springbok Zone to date, with 33 holes totaling 16,950 metres completed in 2024, to establish the 50 x 50 metre spacing that informs this initial Inferred Mineral Resource estimate. Recent drilling at the Springbok Zone remains open southward, indicating additional exploration potential beyond the currently defined resource. The Company determined that the initial Inferred Mineral Resource estimate of 1.75 million tonnes grading 6.91 grams per tonne ("g/t") gold for a total of 390,000 ounces of gold ounces was sufficient to initiate a preliminary economic assessment ("PEA") on development of the deposit by underground mining methods, similar to the Wolfshag deposit. Subject to receipt of a positive PEA and permit, mining of the Springbok Zone, coupled with the exploration potential of the greater Antelope deposit, could begin to contribute to gold production at Otjikoto in 2026. The Antelope deposit has the potential to be developed as an underground mining operation, which could complement the expected processing of low grade stockpiles at the Otjikoto mill from 2026 to 2031. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no guarantee that all or any part of the Mineral Resource will be converted into a Mineral Reserve. Inferred Resources are considered too geologically speculative to have mining and economic considerations applied to them that would enable them to be categorized as Mineral Reserves.

B2Gold has successfully completed the 2024 winter ice road ("WIR") campaign and has delivered all necessary material from the Marine Laydown Area ("MLA") to complete the construction of the Goose Project in the second quarter of 2025. As announced in May 2024, development of the open pit and underground was slightly behind schedule due to equipment availability (commissioning and availability of the open pit equipment), adverse weather conditions and prioritizing of critical path construction activities. The current schedule indicates that an additional three months of mining must be added to the schedule to ensure that the Umwelt open pit, underground development, and crown pillar activities align and that there is sufficient tailings storage capacity in the Echo open pit. With the schedule change, as announced in May 2024, the mill is now scheduled to start wet commissioning in the second quarter of 2025 with ramp up to full production in the third quarter of 2025 (one quarter later than previous estimates). This does not impact the other facets of the project and staffing tables have been adjusted to ensure that capital is conserved. With the updated schedule, the Company estimates that gold production in calendar year 2025 will be between 120,000 ounces and 150,000 ounces (previously estimated to be between 220,000 ounces and 260,000 ounces). Importantly, the updated mining schedule does not impact the total number of gold ounces the Company expects to produce over the life of mine of the Goose Project. The updated production profile has resulted in the Company now estimating that average annual gold production from 2026 to 2030 will increase to be in excess of 310,000 ounces per year (previously estimated at 300,000 ounces per year). All planned construction for the first half of 2024 that is necessary to produce gold by the end of the second quarter of 2025 has been completed and the project development remains on schedule. Development of the open pit and underground remain on the critical path to ensure that adequate material is available for start up and that Echo Pit is available for tailings placement. The open pit started slowly but has shown good progress in the second quarter of 2024 and is meeting production targets and is anticipated to be ready to receive tailings when the mill starts. The underground mine is tracking slightly behind budget but remains on schedule overall for commencement of production by the end of the second quarter of 2025. B2Gold is currently reviewing final options for mining of crown pillar and maximizing volumes of Echo Pit.
4




On June 5, 2024, the Company entered into a purchase and sale agreement (the “Agreement”) to sell a portfolio of 10 precious and base metals royalties (the “Royalties”) to Sandbox Royalties Corp. (“Sandbox”), which has subsequently changed its name to Versamet Royalty Corporation ("Versamet"), a private, returns-focused metals royalty company (the “Transaction”). Under the terms of the Agreement, Versamet will acquire ownership of the Royalties and as consideration will issue 153.2 million common shares to B2Gold at a price of C$0.80 per share, representing an equity ownership interest in Versamet of 33.0% valued at approximately $90 million. The Royalties are comprised of the following:

2.7% net smelter return (“NSR”) royalty on the Kiaka Gold Project, owned by West African Resources Ltd.;
2.7% NSR royalty on the Toega Gold Deposit, owned by West African Resources Ltd.;
2.0% NSR royalty on the Mocoa Project, owned by Libero Copper & Gold Corp.;
1.5% NSR royalty on the Primavera Project, owned by Calibre Mining Corp.; and
Five additional exploration stage royalties.

The closing of the first phase of the Transaction occurred on June 5, 2024, and included the royalties on the Kiaka Gold Project, the Toega Gold Deposit, the Primavera Project, and two exploration stage royalties. In connection with the first phase closing, B2Gold received 122 million shares of Versamet. The remaining royalties are subject to various right of first refusal or right of first offer provisions, which are expected to lapse or be exercised within 60 days of the closing of the first phase, at which time the closing of the second phase of the Transaction is expected to occur.

On June 18, 2024, the Company announced the results a positive PEA prepared in accordance with National Instrument 43-101 (“NI 43-101”) on its 100% owned Gramalote gold project located in the Department of Antioquia, Colombia (the “Gramalote Project”). B2Gold has commenced feasibility work with the goal of completing a feasibility study by mid-2025 and a $10 million budget has been approved by the Board.

On June 20, 2024, the Company completed the sale of an aggregate 79,000,000 common shares of Calibre in the ordinary course for investment purposes by way of a block trade (the “Transaction”) for aggregate gross proceeds of $100 million (C$139 million). Immediately prior to the Transaction, B2Gold owned 110,950,333 common shares of Calibre representing approximately 14.1% of Calibre. As a result of the Transaction, B2Gold’s ownership has decreased to approximately 4.4% and no longer has the right to a seat on the Board of Directors of Calibre. The Company has determined that it no longer has significant influence over Calibre and stopped equity accounting for Calibre June 20, 2024. B2Gold’s decision to dispose of the common shares of Calibre pursuant to the Transaction was made as a result of investment considerations including price, market conditions, capital allocation priorities, and corporate strategy. B2Gold remains a supportive shareholder of Calibre and does not currently plan to make any additional changes to its interest.


5



REVIEW OF FINANCIAL RESULTS
Selected Quarterly Financial and Operating Results
 Three months endedSix months ended
 June 30,June 30,
 2024202320242023
Gold revenue ($ in thousands)492,569470,854954,013944,410
Net (loss) income ($ in thousands)(34,777)91,85013,704193,754
(Loss) earnings per share – basic(1) ($/ share)
(0.02)0.060.010.14
(Loss) earnings per share – diluted(1) ($/ share)
(0.02)0.060.010.14
Cash provided by operating activities ($ thousands)62,432194,983773,159398,806
Average realized gold price ($/ ounce)2,3431,9692,2021,934
Adjusted net income(1)(2) ($ in thousands)
78,44985,804159,952191,666
Adjusted earnings per share(1)(2) – basic ($)
0.060.070.120.16
Consolidated operations results:
Gold sold (ounces)210,228239,100433,206488,250
Gold produced (ounces)204,241245,961418,580496,680
Production costs ($ in thousands)151,299152,762308,044280,366
Cash operating costs(2) ($/ gold ounce sold)
720639711574
Cash operating costs(2) ($/ gold ounce produced)
808607762591
Total cash costs(2) ($/ gold ounce sold)
877777857714
All-in sustaining costs(2) ($/ gold ounce sold)
1,2441,2101,2961,128
Operations results including equity investment in Calibre:
Gold sold (ounces) 218,495255,897452,850521,189
Gold produced (ounces)212,508262,701438,224529,557
Production costs ($ in thousands)164,520170,577333,170313,946
Cash operating costs(2) ($/ gold ounce sold)
753667736602
Cash operating costs(2) ($/ gold ounce produced)
839636785618
Total cash costs(2) ($/ gold ounce sold)
908800879738
All-in sustaining costs(2) ($/ gold ounce sold)
1,2671,2141,3081,135
(1) Attributable to the shareholders of the Company.
(2) Non-IFRS measure. For a description of how these measures are calculated and a reconciliation of these measures to the most directly comparable measures specified, defined or determined under IFRS and presented in the Company’s financial statements, refer to “Non-IFRS Measures”.
Second quarter 2024 and 2023
Revenue
Consolidated gold revenue for the second quarter of 2024 was $493 million on sales of 210,228 ounces at an average price of $2,343 per ounce compared to $471 million on sales of 239,100 ounces at an average price of $1,969 per ounce in the second quarter of 2023. The increase in gold revenue of 5% ($22 million) was attributable to a 19% increase in average realized gold price partially offset by a 12% decrease in gold ounces sold.
In the second quarter of 2024, the Fekola Mine accounted for $271 million (second quarter of 2023 - $282 million) of gold revenue from the sale of 115,288 ounces (second quarter of 2023 - 142,850 ounces), the Masbate Mine accounted for $109 million (second quarter of 2023 - $111 million) of gold revenue from the sale of 46,600 ounces (second quarter of 2023 - 56,700 ounces) and the Otjikoto Mine accounted for $113 million (second quarter of 2023 - $78 million) of gold revenue from the sale of 48,340 ounces (second quarter of 2023 - 39,550 ounces).

Production and operating costs
For the second quarter of 2024, total gold production was 212,508 ounces (including 8,267 ounces of attributable production from Calibre), 4% (9,493 ounces) lower than budget, and lower than the second quarter of 2023 by 19% (50,193 ounces). Consolidated gold production from the Company’s three operating mines was 204,241 ounces in the second quarter of 2024, 3% (6,979 ounces) lower than budget, and 17% (41,720 ounces) lower compared to the second quarter of 2023. For the second quarter of 2024, production from the Masbate and Otjikoto mines was 2% (914 ounces) and 4% (1,643 ounces) higher than
6



budget, respectively, while the Fekola Mine production was 8% (9,536 ounces) lower than budget as a result of equipment availability issues (refer to "Review of Mining Operations and Development Projects" section below). In the second quarter of 2024, the Otjikoto Mine produced 9% (4,087 ounces) more ounces than the second quarter of 2023, while the Fekola and Masbate mines produced 27% (40,844 ounces) and 10% (4,963 ounces) less ounces, respectively, compared to the second quarter of 2023.
For the second quarter of 2024, consolidated cash operating costs (refer to "Non-IFRS Measures") were $808 per gold ounce produced ($720 per gold ounce sold), $57 (7%) lower than budget and $201 (33%) per gold ounce produced higher than the second quarter of 2023. Including estimated attributable results for Calibre, cash operating costs for the second quarter of 2024 were $839 per gold ounce produced ($753 per gold ounce sold), $35 (4%) lower than budget and $203 (32%) per gold ounce produced higher than the second quarter of 2023. Cash operating costs per ounce produced for the second quarter of 2024 were lower than budget largely as a result of lower than budgeted fuel costs, lower tonnage mined at the Fekola Mine due to equipment availability and a weaker Namibian dollar. Compared to the second quarter of 2023, cash operating costs per ounce produced for the second quarter of 2024 were higher mainly due to higher ounces produced in the second quarter of 2023.

Consolidated all-in sustaining costs (refer to "Non-IFRS Measures") for the second quarter of 2024 were $1,244 per gold ounce sold compared to budget of $1,412 per gold ounce sold and $1,210 per gold ounce sold for the second quarter of 2023. Including estimated attributable results for Calibre, all-in sustaining costs for the second quarter of 2024 were $1,267 per gold ounce sold compared to budget of $1,408 per gold ounce sold and $1,214 per gold ounce sold for the second quarter of 2023. All-in sustaining costs for the second quarter of 2024 were $141 (10%) per gold ounce sold lower than budgeted due to lower than budgeted production costs per gold ounce sold and lower than budgeted sustaining capital expenditures, partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures were mainly a result of timing of expenditures and are expected to be incurred later in 2024.
Depreciation and depletion
Depreciation and depletion expense included in total cost of sales was $95 million in the second quarter of 2024 in line with the second quarter of 2023. The increase in depreciation charge per ounce sold was offset by a decrease in gold ounces sold when comparing the second quarter of 2024 to the second quarter of 2023.

Royalties and production taxes
Royalties and production taxes included in total cost of sales were $33 million for the second quarter of 2024 compared to $33 million for the second quarter of 2023. The impact of the increase in realized gold price for the second quarter of 2024 compared to the second quarter of 2023 was offset by a decrease in gold ounces sold and a change in the sales mix in the second quarter of 2024 to include proportionately less gold ounces sold from the Fekola Mine, resulting in an overall lower effective royalty rate for the period.
Other
General and administrative (“G&A”) costs relate primarily to the Company’s head office in Vancouver, the Bamako office in Mali, the Makati office in the Philippines and the Windhoek office in Namibia. G&A for the second quarter of 2024 was $13 million which was 7% lower than the second quarter of 2023 resulting from lower bank charges and lower travel charges.
Share-based payment expense for the second quarter of 2024 was $5 million, which was consistent with the second quarter of 2023.
For the second quarter of 2024, the Company recorded a net impairment charge on the Fekola Complex of $194 million (pre-tax $215 million less $21 million deferred tax recovery) (refer to "Critical Accounting Estimates" section below). For the second quarter of 2023, the Company recorded a $5 million impairment on its investment in BeMetals Corp.
For the second quarter of 2024, the Company recorded a $49 million gain on sale of mining interests in relation to the royalty portfolio sale to Versamet and recorded a $17 million gain on sale of shares in associate in relation to the sale of Calibre shares.
For the second quarter of 2024, the Company's estimate of its share of Calibre's net income based on publicly available information was $3 million (second quarter of 2023 - $7 million).
The Company reported $11 million in foreign exchange losses for the second quarter of 2024 compared to foreign exchange losses of $2 million in the second quarter of 2023 reflecting the weakening of the Malian and Namibian currencies.
The Company reported $7 million in interest and financing expense during the second quarter of 2024 which was $5 million higher than the second quarter of 2023 resulting from financing expense being recorded on the Company's prepaid sales. The Company reported interest income of $8 million in the second quarter of 2024 compared to $6 million in the second quarter of 2023, which was higher due to higher interest rates in the second quarter of 2024.
7



The Company reported a loss on change in fair value of the gold stream obligation of $8 million for the second quarter of 2024 resulting from changes in long-term gold prices and interest rates compared to $1 million for the second quarter of 2023.
For the second quarter of 2024, the Company recorded a net current income and other tax expense of $97 million, compared to $71 million in the second quarter of 2023, consisting of current income tax of $89 million (Q2 2023 - $51 million), the 10% priority dividend to the State of Mali of $5 million (Q2 2023 - $10 million) and withholding tax (on intercompany dividends/management fees) of $2 million (Q2 2023 - $10 million). The priority dividend is accounted for as an income tax in accordance with IAS 12, Income Taxes. Compared to the second quarter of 2023, net current income and other tax expense for the second quarter of 2024 was higher mainly as a result of a tax audit accrual of $37 million partially offset by $9 million higher withholding tax on intercompany dividends in the second quarter of 2023. For the second quarter of 2024, the Company recorded a deferred income tax recovery of $38 million compared to a deferred income tax recovery of $4 million in the second quarter of 2023. The 2024 deferred income tax expense includes $19 million lower future withholding taxes, $7 million higher foreign exchange effects and $22 million lower temporary differences between accounting and taxable income mainly due to the Fekola Complex impairment.

For the second quarter of 2024, the Company generated a net loss of $35 million compared to a net income of $92 million in the second quarter of 2023, including a net loss attributable to the shareholders of the Company of $24 million (net loss attributable to shareholders of the Company of $0.02 per share) in the second quarter of 2024 compared to a net income attributable to the shareholders of the Company of $80 million ($0.06 per share) in the second quarter of 2023. Adjusted net income attributable to the shareholders of the Company (refer to "Non-IFRS Measures") for the second quarter of 2024 was $78 million ($0.06 per share) compared to adjusted net income of $86 million ($0.07 per share) in the second quarter of 2023. Adjusted net income in the second quarter of 2024 excluded the impairment of long-lived assets of $197 million, gain on sale of shares of associate of $17 million, gain on sale of mining interests of $49 million, loss on change in fair value of the gold stream obligation of $8 million and deferred income tax recovery of $37 million.

Cash flow provided by operating activities was $62 million in the second quarter of 2024 compared to $195 million in the second quarter of 2023, a decrease of $133 million due mainly to higher working capital outflows, higher long-term value added tax receivables outflows and higher long-term inventory outflows, partially offset by higher revenues. Cash income and withholding tax payments in the second quarter of 2024 totalled $133 million (second quarter of 2023 - $59 million), including approximately $82 million related to 2023 outstanding tax liability obligations. Based on actual results for the first quarter of 2024 and revised forecast assumptions, including an average forecast gold price of $2,150 per ounce for the balance of 2024 (previously $2,000 per ounce), the Company is now forecasting to make total cash income tax payments for current income tax, withholding and other taxes in 2024 of approximately $289 million (previous estimate was $270 million).

B2Gold continues to maintain a strong financial position and liquidity. At June 30, 2024, the Company had cash and cash equivalents of $467 million (December 31, 2023 - $307 million) and working capital (defined as current assets less assets classified as held for sale and current liabilities) of $600 million (December 31, 2023 - $397 million). At June 30, 2024, the full amount of the Company's $700 million RCF was undrawn and available.

Year to date results
Revenue
Consolidated gold revenue for the first half of 2024 was $954 million on sales of 433,206 ounces at an average price of $2,202 per ounce compared to $944 million on sales of 488,250 ounces at an average price of $1,934 per ounce in the first half of 2023. The increase in gold revenue of 1% ($10 million) was attributable to a 14% increase in average realized gold price partially offset by 11% decrease in gold ounces sold.

In the first half of 2024, the Fekola Mine accounted for $527 million (first half of 2023 - $596 million) of gold revenue from the sale of 239,116 ounces (first half of 2023 - 307,900 ounces), the Masbate Mine accounted for $208 million (first half of 2023 - $168 million) of gold revenue from the sale of 94,300 ounces (first half of 2023 - 86,350 ounces) and the Otjikoto Mine accounted for $219 million (first half of 2023 - $180 million) of gold revenue from the sale of 99,790 ounces (first half of 2023 - 94,000 ounces).
Production and operating costs

For the first half of 2024, total gold production was 438,224 ounces (including 19,644 ounces of attributable production from Calibre), 1% (5,271 ounces) lower than budget, and 17% (91,333 ounces) lower compared to the first half of 2023. Consolidated gold production from the Company’s three operating mines was 418,580 ounces in the first half of 2024, 1% (3,353 ounces) lower than budget and 16% (78,100 ounces) lower compared to the first half of 2023. For the first half of 2024, production from the Masbate and Otjikoto mines was 3% (3,141 ounces) and 4% (3,559 ounces) higher than budget, respectively, while the Fekola Mine production was 4% (10,053 ounces) lower than budget. In the first half of 2024, the Otjikoto Mine produced 13% (11,012 ounces) more ounces than the first half of 2023, while the Fekola and Masbate mines produced 28% (87,567 ounces) and 2% (1,545 ounces) less ounces, respectively, compared to the first half of 2023.

8



For the first half of 2024, consolidated cash operating costs (refer to "Non-IFRS Measures") were $762 per gold ounce produced ($711 per gold ounce sold), $74 (9%) lower than budget and $171 (29%) per gold ounce produced higher than the first half of 2023. Including estimated attributable results for Calibre, cash operating costs for the first half of 2024 were $785 per gold ounce produced ($736 per gold ounce sold), $61 (7%) lower than budget and $167 (27%) per gold ounce produced higher than the first half of 2023. Cash operating costs per ounce produced for the first half of 2024 were lower than budget largely as a result of lower than budgeted fuel costs, lower tonnage mined at the Fekola Mine due to equipment availability and a weaker Namibian dollar. Compared to the first half of 2023, cash operating costs per ounce produced for the first half of 2024 were higher mainly due to higher ounces produced in the first half of 2023.

Consolidated all-in sustaining costs (refer to "Non-IFRS Measures") for the first half of 2024 were $1,296 per gold ounce sold compared to budget of $1,472 per gold ounce sold and $1,128 per gold ounce sold for the first half of 2023. Including estimated attributable results for Calibre, all-in sustaining costs for the first half of 2024 were $1,308 per gold ounce sold compared to budget of $1,465 per gold ounce sold and $1,135 per gold ounce sold for the first half of 2023. Consolidated all-in sustaining costs for the first half of 2024 were $157 (11%) per gold ounce sold lower than budgeted due to lower than budgeted production costs per gold ounce sold, higher gold ounces sold and lower than budgeted sustaining capital expenditures, partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures were mainly a result of timing of expenditures and are expected to be incurred later in 2024.

Depreciation and depletion

Depreciation and depletion expense included in total cost of sales was $185 million for the first half of 2024 compared to $192 million in the first half of 2023. The 4% decrease in depreciation expense was mainly due to an 11% decrease in gold ounces sold partially offset by a 9% increase in depreciation charge per ounce of gold sold.

Royalties and production taxes
Royalties and production taxes included in total cost of sales were $63 million for the first half of 2024 compared to $68 million in the first half of 2023. The 7% decrease in royalties and production taxes was due to a 11% decrease in gold ounces sold, a change in the sales mix in the first half of 2024 to include proportionately less ounces sold from the Fekola Mine, resulting in an overall lower effective royalty rate for the period, partially offset by a 14% increase in the average realized gold price.
Other
G&A costs relate mainly to the Company’s head office in Vancouver, the Bamako office in Mali, the Makati office in the Philippines and the Windhoek office in Namibia. G&A for the first half of 2024 was $27 million, which was consistent with the first half of 2023.
Share-based payment expense for the first half of 2024 was $10 million, which was $1 million lower than the first half of 2023. The lower share-based payment expense resulted from the lower share valuation of grants in the first half of 2024 compared to the first half of 2023.

For the first half of 2024, the Company recorded a net impairment charge for the Fekola Complex of $194 million (pre-tax $215 million less $21 million deferred tax recovery). For the first half of 2023, the Company recorded a $5 million impairment on its investment in BeMetals Corp.
For the first half of 2024, the Company recorded a $49 million gain on sale of mining interests in relation to the royalty portfolio sale to Versamet and recorded a $17 million gain on sale of shares in associate in relation to the sale of Calibre shares.
The Company recorded an expense for non-recoverable input taxes of $7 million in the first half of 2024 compared to $3 million in the first half of 2023.
For the first half of 2024, the Company's estimate of its share of Calibre's net income based on publicly available information was $5 million (first half of 2023 - $12 million).
The Company reported $14 million in foreign exchange losses for the second quarter of 2024 compared to foreign exchange losses of $3 million in the second quarter of 2023 reflecting the weakening of the Malian and Namibian currencies.
For the first half of 2023, the Company recorded a $7 million provision for recognition of Otjikoto severance costs.
For the first half of 2024, other operating expenses totalled $8 million, which included $4 million for non-capital exploration costs and $1 million loss on disposal of assets.
In the first half of 2023, the Company recorded a $16 million write-off of mining interests relating to greenfield exploration targets.
9



The Company reported $17 million in interest and financing expense during the first half of 2024, $11 million higher than the first half of 2023 reflecting the recording of the finance cost associated with the Gold Prepay in the first half of 2024 as well as the finance cost on the RCF for the first half of 2024. Interest income for the first half of 2024 was $13 million compared to $12 million in the first half of 2023.

The Company reported a loss on change in fair value of the gold stream obligation of $19 million for the first half of 2024 resulting from changes in long-term gold prices and interest rates compared to $1 million for the first half of 2023.
For the first half of 2024, the Company recorded a dilution loss on investment in Calibre of $9 million mainly relating to the dilution of the Company's investment in Calibre from 24% to 15% as a result of Calibre's acquisition of Marathon Gold Corp., which closed in January 2024.

For the first half of 2024, the Company recorded current income tax, withholding and other tax expense of $158 million compared to $148 million in the first half of 2023, consisting of current income tax expense of $140 million (first half of 2023 - $117 million), the 10% priority dividend to the State of Mali of $13 million (first half of 2023 - $19 million) and withholding tax (on intercompany dividends/management fees) of $5 million (first half of 2023 - $12 million). The priority dividend is accounted for as an income tax in accordance with IAS 12, Income Taxes. Compared to the first half of 2023, current tax expense for the first half of 2024 was higher mainly as a result of a tax audit accrual of $37 million which was partially offset by lower income and lower withholding taxes on intercompany dividends in Fekola. For the first half of 2024, the Company recorded a deferred income tax recovery of $18 million compared to a deferred income tax recovery of $5 million in the first half of 2023. The deferred income tax expense for the first half of 2024 includes $10 million lower future withholding taxes, $19 million higher foreign exchange effects and $22 million lower temporary differences between accounting and taxable income mainly due to the Fekola Complex impairment.

For the first half of 2024, the Company generated net income of $14 million compared to net income of $194 million in the first half of 2023, including net income attributable to the shareholders of the Company of $16 million ($0.01 per share) in the first half of 2024 compared to $166 million ($0.14 per share) in the first half of 2023. Adjusted net income attributable to the shareholders of the Company (refer to “Non-IFRS Measures”) for the first half of 2024 was $160 million ($0.12 per share) compared to adjusted net income of $192 million ($0.16 per share) in the first half of 2023. Adjusted net income in the first half of 2024 excluded the impairment of long-lived assets of $197 million, gain on sale of shares of associate of $17 million, gain on sale of mining interests of $49 million, loss on change in fair value of the gold stream obligation of $19 million, dilution loss on investment in Calibre of $9 million and deferred income tax recovery of $16 million.

Cash flow provided by operating activities was $773 million in the first half of 2024 compared to $399 million in the first half of 2023, an increase of $374 million due mainly to $500 million of proceeds received from the Gold Prepay in January 2024, higher revenues, partially offset by higher production costs, higher working capital outflows and higher long-term inventory outflows. Cash income and withholding tax payments in the first half of 2024 totalled $172 million (first half of 2023 - $90 million), including approximately $88 million related to 2023 outstanding tax liability obligations. Based on actual results for the first quarter of 2024 and revised forecast assumptions, including an average forecast gold price of $2,150 per ounce for the balance of 2024 (previously $2,000 per ounce), the Company is now forecasting to make total cash income tax payments for current income tax, withholding and other taxes in 2024 of approximately $289 million (previous estimate was $270 million).
10



REVIEW OF MINING OPERATIONS AND DEVELOPMENT PROJECTS
Fekola Mine - Mali
 Three months endedSix months ended
 June 30,June 30,
 2024202320242023
Gold revenue ($ in thousands)270,592281,672526,910595,897
Gold sold (ounces)115,288142,850239,116307,900
Average realized gold price ($/ ounce)2,3471,9722,2041,935
Tonnes of ore milled2,520,3772,324,0434,983,2404,595,934
Grade (grams/ tonne)1.512.241.572.36
Recovery (%)92.891.892.791.9
Gold production (ounces)111,583152,427230,724318,291
Production costs ($ in thousands)81,48179,245166,586156,906
Cash operating costs(1) ($/ gold ounce sold)
707555697510
Cash operating costs(1) ($/ gold ounce produced)
839538766509
Total cash costs(1) ($/ gold ounce sold)
895721873673
All-in sustaining costs(1) ($/ gold ounce sold)
1,2581,1651,3511,057
Capital expenditures ($ in thousands)53,17974,151133,741127,946
Exploration ($ in thousands)8382,1401,706
(1) Non-IFRS measure. For a description of how these measures are calculated and a reconciliation of these measures to the most directly comparable measures specified, defined or determined under IFRS and presented in the Company’s financial statements, refer to “Non-IFRS Measures”.

The Fekola Mine in Mali (owned 80% by the Company and 20% by the State of Mali) produced 111,583 ounces of gold in the second quarter of 2024, 8% (9,536 ounces) below budget and 27% (40,844 ounces) lower than the second quarter of 2023. For the second quarter of 2024, mill feed grade was 1.51 g/t compared to budget of 1.74 g/t and 2.24 g/t in the second quarter of 2023; mill throughput was 2.52 million tonnes compared to budget of 2.38 million tonnes and 2.32 million tonnes in the second quarter of 2023; and gold recovery averaged 92.8% compared to budget of 90.9% and 91.8% in the second quarter of 2023. Gold production for the second quarter of 2024 was lower than budget due to the delayed timing of mining of high grade ore as compared to budget, resulting in less high grade ore processed during the second quarter of 2024. Damage to an excavator and the subsequent need for replacement equipment impacted equipment availability for the second quarter and first half of 2024, reducing tonnes mined. These equipment availability issues are being addressed and mining rates are expected to improve by the end of the third quarter of 2024. The reduction in mining rate capacity experienced in 2024 is expected to impact the availability of higher grade ore from Phase 7 of the Fekola pit during the second half of 2024 resulting in an expected decrease of approximately 50,000 ounces in Fekola production for full year 2024. Mining and processing of those ounces is now expected in the first half of 2025. Ore volumes and grades continue to reconcile well with modelled values. Gold production for the second quarter of 2024 was also lower than the second quarter of 2023, as the second quarter of 2023 benefitted from a favourable 2023 mine phasing sequence with Phase 6 of the Fekola pit providing significant high-grade ore to the process plant. For the first half of 2024, gold production was 230,724 ounces, 4% (10,053 ounces) below budget and 28% (87,567 ounces) lower than the first half of 2023. For the first half of 2024, mill feed grade was 1.57 g/t compared to budget of 1.78 g/t and 2.36 g/t in the first half of 2023; mill throughput was 4.98 million tonnes compared to budget of 4.62 million tonnes and 4.60 million tonnes in the first half of 2023; and gold recovery averaged 92.7% compared to budget of 90.9% and 91.9% in the first half of 2023.

The Fekola Mine’s cash operating costs (refer to “Non-IFRS Measures”) for the second quarter of 2024 were $839 per ounce produced ($707 per gold ounce sold) compared to a budget of $927 per ounce produced and $538 per ounce produced for the second quarter of 2023. Cash operating costs per ounce produced for the second quarter of 2024 were $88 (9%) per ounce produced lower than budget as a result of lower fuel costs, higher mill throughput, higher gold recovery and lower mining costs due to lower than budgeted mined tonnage due to equipment availability. Cash operating costs per ounce produced for the second quarter of 2024 were $301 (56%) per ounce produced higher than the second quarter of 2023 due primarily to the planned decrease in gold production in the second quarter of 2024. The Fekola Mine’s cash operating costs for the first half of 2024 were $766 per ounce produced ($697 per gold ounce sold) compared to a budget of $863 per ounce produced and $509 per ounce produced for the first half of 2023. Cash operating costs per ounce produced for the first half of 2024 were $97 (11%) per ounce produced lower than budget as a result of lower fuel costs, higher mill throughput, higher gold recovery and lower mining costs due to lower than budgeted mined tonnage due to equipment availability. Compared to the first half of 2023, cash operating costs per ounce produced for the first quarter of 2024 were $257 (50%) higher due primarily to the planned decrease in gold production in the first half of 2024.

11



All-in sustaining costs (refer to “Non-IFRS Measures”) for the second quarter of 2024 were $1,258 per gold ounce sold compared to a budget of $1,482 per gold ounce sold and $1,165 per gold ounce sold in the second quarter of 2023. All-in sustaining costs for the second quarter of 2024 were $224 (15%) per gold ounce sold lower than budget as a result of lower than budgeted production costs per gold ounce sold and lower than budgeted sustaining capital expenditures ($8 million) partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. All-in sustaining costs for the first half of 2024 were $1,351 per gold ounce sold compared to a budget of $1,550 per gold ounce sold and $1,057 per gold ounce sold in the first half of 2023. All-in sustaining costs for the first half of 2024 were $199 (13%) per gold ounce sold lower than budget as a result of lower than budgeted production costs per gold ounce sold and lower than budgeted sustaining capital expenditures ($18 million), partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures for the second quarter of 2024 and the first half of 2024 were mainly a result of timing of expenditures and are expected to be incurred later in 2024.

Capital expenditures in the second quarter of 2024 totalled $53 million primarily consisting of $13 million for deferred stripping, $9 million for mobile equipment purchases and rebuilds, $9 million for the construction of a new TSF, $15 million for Fekola underground development, $4 million for solar plant expansion and $2 million for power generation. Capital expenditures in the first half of 2024 totalled $134 million primarily consisting of $42 million for deferred stripping, $26 million for mobile equipment purchases and rebuilds, $21 million for the construction of a new TSF, $26 million for Fekola underground development, $7 million for solar plant expansion and $2 million for haul road construction.

As a result of the delay in accessing higher grade ounces from Phase 7 of the Fekola pit as discussed above, the Fekola Complex in Mali is now expected to produce between 420,000 and 450,000 ounces of gold in 2024 (original guidance of between 470,000 and 500,000 ounces) at cash operating costs of between $870 and $930 per ounce (original guidance range of between $835 and $895 per ounce) and all-in sustaining costs of between $1,510 and $1,570 per ounce (original guidance of between $1,420 and $1,480 per ounce). The Fekola Complex’s total 2024 gold production is also lower relative to 2023 due to lower production at the Fekola Complex as a result of the delay in receiving an exploitation license for Fekola Regional delaying the 80,000 to 100,000 ounces that were scheduled in the life-of-mine plan to be trucked to the Fekola mill and processed in 2024 but now expected to commence in 2025.

Masbate Mine – Philippines
 Three months endedSix months ended
 June 30,June 30,
 2024202320242023
Gold revenue ($ in thousands)109,083111,291208,050168,283
Gold sold (ounces)46,60056,70094,30086,350
Average realized gold price ($/ ounce)2,3411,9632,2061,949
Tonnes of ore milled2,043,0572,000,3604,212,5194,069,402
Grade (grams/ tonne)0.941.030.960.99
Recovery (%)72.474.372.473.9
Gold production (ounces)44,51549,47894,29795,842
Production costs ($ in thousands)37,60248,17080,37373,163
Cash operating costs(1) ($/ gold ounce sold)
807850852847
Cash operating costs(1) ($/ gold ounce produced)
876817854849
Total cash costs(1) ($/ gold ounce sold)
955960983971
All-in sustaining costs(1) ($/ gold ounce sold)
1,1351,0911,1771,169
Capital expenditures ($ in thousands)6,5076,09815,03715,051
Exploration ($ in thousands)9281,0081,7491,967
(1) Non-IFRS measure. For a description of how these measures are calculated and a reconciliation of these measures to the most directly comparable measures specified, defined or determined under IFRS and presented in the Company’s financial statements, refer to “Non-IFRS Measures”.

The Masbate Mine in the Philippines continued its strong performance, with second quarter of 2024 gold production of 44,515 ounces, above budget by 2% (914 ounces) and 10% (4,963 ounces) lower than the second quarter of 2023 due to lower grade and lower gold recovery. For the second quarter of 2024, mill feed grade was 0.94 g/t compared to budget of 0.93 g/t and 1.03 g/t in the second quarter of 2023; mill throughput was 2.04 million tonnes compared to budget of 1.93 million tonnes and 2.00 million tonnes in the second quarter of 2023; and gold recovery averaged 72.4% compared to budget of 75.8% and 74.3% in the second quarter of 2023. Lower gold recovery for the second quarter of 2024 as compared to budget is the result of mining additional lower recovery high grade sulphide ore during the second quarter of 2024 as compared to budget. Actual gold recovery for the second quarter of 2024 remained in line with modeled recovery values for the ore mined. For the first half of 2024, the Masbate Mine had gold production of 94,297 ounces, above budget by 3% (3,141 ounces) and 2% (1,545 ounces) lower than the first half of 2023. For the first half of 2024, mill feed grade was 0.96 g/t compared to budget of 0.96 g/t and 0.99 g/t in the first half of 2023; mill throughput was 4.21 million tonnes compared to budget of 3.93 million tonnes and 4.07 million tonnes in the first half of 2023; and gold recovery averaged 72.4% compared to budget of 75.3% and 73.9% in the first half of 2023.

12



The Masbate Mine's cash operating costs (refer to “Non-IFRS Measures”) for the second quarter of 2024 were $876 per ounce produced ($807 per gold ounce sold) compared to a budget of $979 per ounce produced and $817 per ounce produced for the second quarter of 2023. Cash operating costs per ounce produced for the second quarter of 2024 were $103 (11%) per ounce produced lower than budget as a result of higher than budgeted gold production and lower than anticipated mining and processing costs due to higher productivity and lower diesel and heavy fuel oil costs. Cash operating costs per ounce produced for the second quarter of 2024 were $59 (7%) per ounce produced higher than the second quarter of 2023 due primarily to lower gold production in the second quarter of 2024. The Masbate Mine's cash operating costs for the first half of 2024 were $854 per ounce produced ($852 per gold ounce sold) compared to a budget of $950 per ounce produced and $849 per ounce produced for the first half of 2023. The variances in cash operating costs per ounce produced for the first half of 2024 compared to budget and the first half of 2023 were the same as noted for the second quarter of 2024.

All-in sustaining costs (refer to “Non-IFRS Measures”) for the second quarter of 2024 were $1,135 per ounce sold compared to a budget of $1,326 per gold ounce sold and $1,091 per gold ounce sold in the second quarter of 2023. All-in sustaining costs for the second quarter of 2024 were $191 (14%) per gold ounce sold lower than budget as a result of lower than budgeted production costs per gold ounce sold. All-in sustaining costs for the first half of 2024 were $1,177 per ounce sold compared to a budget of $1,317 per gold ounce sold and $1,169 per gold ounce sold in the first half of 2023. All-in sustaining costs for the first half of 2024 were $140 (11%) per gold ounce sold lower than budget as a result of lower than budgeted production costs per gold ounce sold and lower than budgeted sustaining capital expenditures ($5 million), partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures were mainly a result of timing of expenditures and are expected to be incurred later in 2024.

Capital expenditures in the second quarter of 2024 totalled $7 million, primarily consisting of $2 million for mobile equipment purchases and rebuilds, $2 million for process plant maintenance, $1 million for expansion of the existing TSF, and $1 million for deferred stripping. Capital expenditures in the first half of 2024 totalled $15 million, primarily consisting of $7 million for mobile equipment purchases and rebuilds, $3 million for process plant maintenance, $1 million for expansion of the existing TSF, and $2 million for deferred stripping.

The Masbate Mine in the Philippines is now expected to produce between 175,000 and 195,000 ounces of gold in 2024 (original guidance range of between 170,000 and 190,000 ounces) at cash operating costs of between $910 and $970 per ounce (original guidance range of between $945 and $1,005 per ounce) and all-in sustaining costs of between $1,260 and $1,320 per ounce (original guidance range of between $1,300 and $1,360 per ounce). Gold production is scheduled to be relatively consistent throughout 2024. For 2024, Masbate is expected to process 7.9 million tonnes of ore at an average grade of 0.93 g/t with a process gold recovery of 76.0%. Mill feed will be a blend of mined fresh ore and low-grade ore stockpiles.

Otjikoto Mine - Namibia
 Three months endedSix months ended
 June 30,June 30,
 2024202320242023
Gold revenue ($ in thousands)112,89477,891219,053180,230
Gold sold (ounces)48,34039,55099,79094,000
Average realized gold price ($/ ounce)2,3351,9692,1951,917
Tonnes of ore milled850,649875,0551,677,1261,699,007
Grade (grams/ tonne)1.791.591.761.53
Recovery (%)98.698.798.598.7
Gold production (ounces)48,14344,05693,55982,547
Production costs ($ in thousands)32,21625,34761,08550,297
Cash operating costs(1) ($/ gold ounce sold)
666641612535
Cash operating costs(1) ($/ gold ounce produced)
673611658609
Total cash costs(1) ($/ gold ounce sold)
760720700612
All-in sustaining costs(1) ($/ gold ounce sold)
1,0441,1871,0001,024
Capital expenditures ($ in thousands)11,70615,63025,51932,976
Exploration ($ in thousands)1,5149963,3031,490
(1) Non-IFRS measure. For a description of how these measures are calculated and a reconciliation of these measures to the most directly comparable measures specified, defined or determined under IFRS and presented in the Company’s financial statements, refer to “Non-IFRS Measures”.

The Otjikoto Mine in Namibia, in which the Company holds a 90% interest, continued to outperform during the second quarter of 2024, producing 48,143 ounces of gold, above budget by 4% (1,643 ounces) as a result of higher than budgeted mill feed grade. Compared to the second quarter of 2023, gold production in the second quarter of 2024 was higher by 9% (4,087 ounces), mainly due to improved processed grade as a result of additional high-grade ore mined from the Wolfshag underground mine in the second quarter of 2024. For the second quarter of 2024, mill feed grade was 1.79 g/t compared to budget of 1.74 g/t and 1.59 g/t in the second quarter of 2023; mill throughput was 0.85 million tonnes compared to budget of 0.85 million tonnes and 0.88 million tonnes in the second quarter of 2023; and gold recovery averaged 98.6% compared to budget of 98.0% and 98.7%
13



in the second quarter of 2023. For the first half of 2024, the Otjikoto Mine produced 93,559 ounces of gold, above budget by 4% (3,559 ounces) and 13% (11,012 ounces) higher compared to the first half of 2023. For the first half of 2024, mill feed grade was 1.76 g/t compared to budget of 1.68 g/t and 1.53 g/t in the first half of 2023; mill throughput was 1.68 million tonnes compared to budget of 1.70 million tonnes and 1.70 million tonnes in the first half of 2023; and gold recovery averaged 98.5% compared to budget of 98.0% and 98.7% in the first half of 2023.

Ore production from the Wolfshag underground mine for the second quarter of 2024 averaged over 1,500 tonnes per day at an average grade of 4.69 g/t gold. As of the beginning of 2024, the Probable Mineral Reserve estimate for the Wolfshag deposit included 100,000 ounces of gold in 0.6 million tonnes of ore at an average grade of 5.02 g/t gold. Open pit mining operations at the Otjikoto Mine will continue to ramp down in 2024 and are expected to conclude in 2025, while processing operations are expected to continue until economically viable stockpiles are exhausted in 2031. Underground operations are currently projected to continue into 2026 with potential to extend underground operations if the ongoing underground exploration program is successful in identifying more underground mineral deposits.

On January 31, 2024, the Company announced positive exploration drilling results from the Antelope deposit at the Otjikoto Mine. The Antelope deposit, which comprises the Springbok Zone, the Oryx Zone, and a possible third structure, Impala, subject to further confirmatory drilling, is located approximately 3 km south of the Otjikoto open pit. On June 20, 2024, the Company announced an initial Inferred Mineral Resource estimate for the Springbok Zone, the southernmost shoot of the recently discovered Antelope deposit. Over 36,000 metres have been drilled into the Springbok Zone to date, with 33 holes totaling 16,950 metres completed in 2024, to establish the 50 x 50 metre spacing that informs this initial Inferred Mineral Resource estimate. Recent drilling at the Springbok Zone remains open southward, indicating additional exploration potential beyond the currently defined resource. The Company determined that the initial Inferred Mineral Resource estimate of 1.75 million tonnes grading 6.91 g/t gold for a total of 390,000 ounces of gold ounces was sufficient to initiate a PEA on development of the deposit by underground mining methods, similar to the Wolfshag deposit. Subject to receipt of a positive PEA and permit, mining of the Springbok Zone, coupled with the exploration potential of the greater Antelope deposit, could begin to contribute to gold production at Otjikoto in 2026. The Antelope deposit has the potential to be developed as an underground mining operation, which could complement the expected processing of low grade stockpiles at the Otjikoto mill from 2026 to 2031. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no guarantee that all or any part of the Mineral Resource will be converted into a Mineral Reserve. Inferred Mineral Resources are considered too geologically speculative to have mining and economic considerations applied to them that would enable them to be categorized as Mineral Reserves.

Cash operating costs (refer to “Non-IFRS Measures”) for the second quarter of 2024 were $673 per gold ounce produced ($666 per ounce gold sold), compared to a budget of $596 per ounce produced and $611 per ounce produced for the second quarter of 2023. Cash operating costs per ounce produced for the second quarter of 2024 were $77 (13%) per gold ounce produced higher than budget due to lower than expected credits for deferred stripping resulting from more ore being mined than budgeted and lower capitalized underground development credits for the second quarter of 2024. Cash operating costs per gold ounce produced for the second quarter of 2024 were $62 (10%) per gold ounce produced higher than the cash operating costs per ounce produced for the second quarter of 2023 due lower mining costs in the second quarter of 2023. Cash operating costs for the first half of 2024 were $658 per gold ounce produced ($612 per ounce gold sold), compared to a budget of $649 per ounce produced and $609 per ounce produced for the first half of 2023. Cash operating costs per ounce produced for the first half of 2024 were $9 (1%) per gold ounce produced higher than budget. Cash operating costs per gold ounce produced for the first half of 2024 were $49 (8%) per gold ounce produced higher than the cash operating costs per ounce produced for the first half of 2023 due to higher mining and processing costs in the first half of 2024.

All-in sustaining costs (refer to “Non-IFRS Measures”) for the second quarter of 2024 were $1,044 per gold ounce sold compared to a budget of $1,015 per gold ounce sold and $1,187 per gold ounce sold in the second quarter of 2023. All-in sustaining costs for the second quarter of 2024 were $29 (3%) per gold ounce sold higher than budget as a result of higher than budgeted cash operating costs described above as well as higher gold royalties resulting from a higher than budgeted average realized gold price, partially offset by lower than expected sustaining capital expenditures and higher than expected gold ounces sold. All-in sustaining costs for the first half of 2024 were $1,000 per gold ounce sold compared to a budget of $1,088 per gold ounce sold and $1,024 per gold ounce sold in the first half of 2023. All-in sustaining costs for the first half of 2024 were $88 (8%) per gold ounce sold lower than budget as a result of lower than budgeted cash operating costs per gold ounce sold, higher than budgeted gold ounces sold and lower than budgeted sustaining capital expenditures ($4 million) partially offset by higher gold royalties resulting from a higher than budgeted average realized gold price. The lower sustaining capital expenditures were mainly a result of timing of expenditures and are expected to be incurred later in 2024.

Capital expenditures for the second quarter of 2024 totalled $12 million consisting of $9 million for deferred stripping in the Otjikoto pit, $2 million for Wolfshag underground mine development, and $1 million for mining equipment rebuilds. Capital expenditures for the first half of 2024 totalled $26 million, consisting of $20 million for deferred stripping in the Otjikoto pit and $5 million for Wolfshag underground mine development.

The Otjikoto Mine in Namibia is now expected to produce between 185,000 and 205,000 ounces of gold in 2024 (original guidance range of between 180,000 and 200,000 ounces of gold) at cash operating costs in the upper end of its guidance range of between $685 and $745 per ounce and all-in sustaining costs of between $960 and $1,020 per ounce. Gold production at Otjikoto is expected to be relatively consistent throughout 2024. Otjikoto is expected to process a total of 3.4 million tonnes of ore at an average grade of 1.77 g/t gold with a process gold recovery of 98.0%. Processed ore will be sourced from the Otjikoto pit and the Wolfshag underground mine, supplemented by existing medium and high-grade ore stockpiles.
14




Investment in Calibre

On January 24, 2024, Calibre completed its acquisition of Marathon Gold Corp. and issued 249,813,422 Calibre common shares reducing B2Gold's ownership interest in Calibre to approximately 15%. As a result of the acquisition, Calibre acquired a 100% interest in the advanced-stage Valentine Gold Project in Newfoundland & Labrador.

On June 20, 2024, the Company completed the sale of an aggregate 79,000,000 common shares of Calibre in the ordinary course for investment purposes by way of a block trade (the “Transaction”) for aggregate gross proceeds of $100 million (C$139 million). Immediately prior to the Transaction, B2Gold owned 110,950,333 common shares of Calibre representing approximately 14.1% of Calibre. As a result of the Transaction, B2Gold’s ownership has decreased to approximately 4.4% and the Company no longer has the right to a nominee to the Board of Directors of Calibre. The Company has determined that it no longer has significant influence over Calibre and will stop equity accounting for Calibre effective June 20, 2024. B2Gold’s decision to dispose of the common shares of Calibre pursuant to the Transaction was made as a result of investment considerations including price, market conditions, capital allocation priorities, and corporate strategy.

For the first half of 2024, the Company's estimate of its share of Calibre's net income based on publicly available information was approximately $5 million. Calibre will report its second quarter of 2024 financial results on August 12, 2024. The Company will update any differences in the third quarter of 2024.

Attributable share of Calibre production and costs

Based on Calibre's production press release dated July 9, 2024, consolidated production of Calibre for the second quarter of 2024 was 58,754 ounces of which the Company's attributable share was 8,267 ounces and for the first half of 2024 was 120,521 ounces of which the Company's attributable share was 19,644 ounces.

The Company has assumed that the consolidated cash operating costs per ounce produced and all-in sustaining costs for Calibre for the second quarter of 2024 will be consistent with the first quarter of 2024.

Goose Project - Canada

The Back River Gold District consists of five mineral claims blocks along an 80 km belt. The most advanced project in the district, Goose, is fully permitted, construction has commenced, and has been de-risked with significant infrastructure currently in place. B2Gold’s management team has strong northern construction expertise and the experience to deliver the fully permitted Goose Project and the financial resources to develop the significant gold resource endowment at the Back River Gold District into a large, long life mining complex.

B2Gold recognizes that respect and collaboration with the Kitikmeot Inuit Association ("KIA") is central to the license to operate in the Back River Gold District and will continue to prioritize developing the project in a manner that recognizes Inuit priorities, addresses concerns and brings long-term socio-economic benefits to the Kitikmeot Region. B2Gold looks forward to continuing to build on its strong collaboration with the KIA and Kitikmeot communities.

At the Back River Gold District, B2Gold operates a sealift program in the summer months and delivers construction and operating materials to the MLA in Bathurst Inlet, Nunavut. An approximately 162 km WIR is constructed by contractors, under B2Gold management, on an annual basis from December to February. The materials are then transported from the MLA to the Goose Project via the WIR during the months of March and April (the “WIR Campaign").

As announced in May 2024, development of the open pit and underground was slightly behind schedule due to equipment availability (commissioning and availability of the open pit equipment), adverse weather conditions and prioritizing of critical path construction activities. The current schedule indicates that an additional three months of mining must be added to the schedule to ensure that the Umwelt open pit, underground development, and crown pillar activities align and that there is sufficient tailings storage capacity in the Echo open pit. With the schedule change, as announced in May 2024, the mill is now scheduled to start wet commissioning in the second quarter of 2025 with ramp up to full production in the third quarter of 2025 (one quarter later than previous estimates). This does not impact the other facets of the project and staffing tables have been adjusted to ensure that capital is conserved. With the updated schedule, the Company estimates that gold production in calendar year 2025 will be between 120,000 ounces and 150,000 ounces (previously estimated to be between 220,000 ounces and 260,000 ounces). Importantly, the updated mining schedule does not impact the total number of gold ounces the Company expects to produce over the life of mine of the Goose Project. The updated production profile has resulted in the Company now estimating that average annual gold production from 2026 to 2030 will increase to be in excess of 310,000 ounces per year (previously estimated at 300,000 ounces per year).

The 2024 WIR Campaign was completed on April 30, 2024, and B2Gold is pleased to report the Company has successfully delivered all necessary materials required to complete construction of the Goose Project. Materials shipped from the MLA to the Goose Project site during the 2024 WIR Campaign exceeded 2,100 standard total loads, including 400 loads of diesel fuel. Under B2Gold management, the 2,100 standard loads completed during the 2024 WIR Campaign is approximately double the loads completed during the 2023 WIR Campaign. Key materials delivered during the 2024 WIR Campaign included:

All modular units necessary to expand the camp to 500 person capacity;
15



All steel and rebar necessary to complete the mill and concrete work;
Approximately 19 million liters of fuel that will be used between May 2024 and March 2025;
All cement necessary to complete the construction project;
More than 4,500 m3 of cement in one tonne bags; and
All reagents necessary to commission and operate the mill starting in 2025.

All planned construction for the first half of 2024 that is necessary to produce gold by the end of the second quarter of 2025 has been completed and the project development remains on schedule. The key items that needed to be completed included:

The installation of Phase 2 of the camp: Completed and camp capacity is now at more than 600 beds;
Construction of tanks to accommodate more than 80 million litres of fuel at the marine laydown area (MLA): Completed. It is anticipated that the MLA will begin to receive fuel in August 2024;
Construction of tanks to accommodate more than 80 million liters of fuel on site: 4 of 5 tanks have been installed with the fifth tank to be completed in third quarter of 2024;
Purchase of materials necessary to complete construction and staging them for shipment to the MLA: Ten ships have been scheduled (7 ships with dry cargo of more than 120,000 m3 and 3 ships with more than 80 million liters of fuel) and prepared to depart for the MLA in August and September, 2024;
All additional trucks have been purchased for shipping materials up the WIR in 2024/2025: An total of 105 trucks will be available to haul fuel and dry goods along an ice road that will be maintained with an expanded fleet of equipment that are expected to commence to work in January 2025 and expected to deliver all goods to site by May 15, 2025;
Concrete placement: More than 75% of all concrete has been placed by the end of the second quarter of 2024 and more than 90% of concrete is expected to be placed by the end of third quarter of 2024;
All E-houses have been placed on the mill pad and electricians are working on connecting power to the various components;
Piping: piping has focused on the diesel tanks and the final Heavy Mechanical Equipment workshop; and
Fresh water barge: Access has been developed for placement of piping and barge for fresh water system. It is anticipated that this will be installed in the third quarter of 2024.

Development of the open pit and underground remain on the critical path to ensure that adequate material is available for start up and that Echo Pit is available for tailings placement. The open pit started slowly but has shown good progress in the second quarter of 2024 and is meeting production targets and is anticipated to be ready to receive tailings when the mill starts. The underground mine is tracking slightly behind budget but remains on schedule overall for commencement of production by the end of the second quarter of 2025. B2Gold is currently reviewing final options for mining of crown pillar and maximizing volumes of Echo Pit.

After completing a detailed design review of the Goose Project, B2Gold announced in January 2024 a revised construction capital estimate to C$1,050 million. In addition, before wet commissioning the Company estimated it will spend an additional C$200 million on underground development, deferred stripping and sustaining capital, as well as an additional C$205 million for fuels, reagents, and other working capital items necessary to build up site inventory levels due to the seasonality of the project logistics. In the second quarter of 2024 and first half of 2024, the Company incurred cash expenditures of $128 million (C$175 million) and $245 million (C$333 million), respectively, for the Goose Project on construction activities and $43 million (C$58 million) and $45 million (C$61 million), respectively on supplies inventory.

B2Gold is currently updating the budget to incorporate the (previously announced) three month delay in commencement of operations and additional costs associated with logistics of shipping materials to site via air transport. A final updated budget is expected to be released in early September 2024.

Fekola Complex - Fekola Mine and Fekola Regional Development

The Fekola Complex is comprised of the Fekola Mine (Medinandi permit hosting the Fekola and Cardinal pits and Fekola underground) and Fekola Regional (Anaconda Area (Bantako, Menankoto and Bakolobi permits) and the Dandoko permit).

The development of Fekola Regional is expected to demonstrate positive economics through the enhancement of the overall production profile and the extension of mine life of the Fekola Complex. Based on B2Gold's preliminary planning, Fekola Regional could provide selective higher grade saprolite material (average annual grade of up to 2.2 g/t gold) to be trucked approximately 20 km and fed into the Fekola mill at a rate of up to 1.5 million tonnes per annum. Trucking of selective higher grade saprolite material from the Anaconda Area to the Fekola mill will increase the ore processed and has the potential to generate approximately 80,000 to 100,000 ounces of additional gold production per year from Fekola Regional sources.

16



Gramalote Project - Colombia

The Gramalote Project is located in central Colombia, approximately 230 km northwest of Bogota and 100 km northeast of Medellin, in the Province of Antioquia, which has expressed a positive attitude towards the development of responsible mining projects in the region. Based on the preliminary results completed in 2022 of the contemplated large-scale project with AngloGold Ashanti Limited (“AngloGold”), the project did not meet the combined investment return thresholds for development by both 50% ownership partners, B2Gold and AngloGold. As a result, B2Gold and AngloGold explored alternatives for the project which resulted in B2Gold acquiring AngloGold’s 50% interest in the Gramalote Project, resulting in a sole owner of the Gramalote Project for the first time in recent history. Post consolidation, B2Gold completed a detailed review of the Gramalote Project, including the higher-grade core of the resource, facility size and location, power supply, mining and processing options, tailings design, resettlement, potential construction sequencing and camp design to identify potential cost savings to develop a medium-scale project. The results of the review allowed the Company to determine the optimal parameters and assumptions for the Gramalote PEA.

The Gramalote PEA, with an effective date of April 1, 2024, was prepared by B2Gold and evaluates recovery of gold from an open pit mining operation that will move up to approximately 97,000 tonnes per day (“tpd”) (35.3 Mtpa), with an approximately 16,500 tpd (6.0 Mtpa) processing plant that includes crushing, grinding, flotation, with fine grinding of the flotation concentrate and agitated leaching of the flotation concentrate followed by a carbon-in-pulp recovery process to process doré bullion. The Mineral Resource estimate for the Gramalote Project that forms the basis for the Gramalote PEA includes Indicated Mineral Resources of 192.2 million tonnes grading 0.68 g/t gold for a total of 4,210,000 ounces of gold and Inferred Mineral Resources of 85.4 million tonnes grading 0.54 g/t gold for a total of 1,480,000 ounces of gold.

Based on the positive results from the Gramalote PEA, B2Gold believes that the Gramalote Project has the potential to become a medium-scale, low-cost, open pit gold mine. The Gramalote Project has several key infrastructure advantages, including:

Reliable water supply – high rainfall region and located next to the Nus River;
Adjacent to a national highway, which connects directly to Medellin and to a major river with port facilities, capable of bringing supplies by barge to within 70 km of the site; and
Skilled labour workforce within Colombia.

In addition, B2Gold expects the Gramalote Project to benefit from several key operational advantages, including:

Excellent metallurgical characteristics of the ore, which results in high recovery rates at low processing costs;
Relatively low strip ratio (3.3:1 strip ratio over the Life of Project); and
Ability to mine and process higher-grade ore in the initial years of the mine life resulting in improved project economics.

The Gramalote PEA is subject to a number of assumptions and risks, including among others that a Modified Environmental Impact Study will be approved, all required permits, permit amendments and other rights will be obtained in a timely manner, the Gramalote Project will have the support of the local government and community, the regulatory environment will remain consistent, that Gramalote can operate under a single company free trade zone in Colombia, and no material increase will have occurred to the estimated costs.

The Gramalote PEA is preliminary in nature and includes a small amount of Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the Gramalote PEA based on these Mineral Resources will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

B2Gold has commenced feasibility work with the goal of completing a feasibility study by mid-2025 and a $10 million budget has been approved by the B2Gold Board of Directors (the "Board"). Due to the work completed for previous studies, the work remaining to finalize a feasibility study for the updated medium-scale project is not extensive. The main work programs for the feasibility study include geotechnical and environmental site investigations for the processing plant and waste dump footprints, as well as capital and operating cost estimates.

The Gramalote Project will continue to advance resettlement programs, establish coexistence programs for small miners, work on health, safety and environmental projects and continue to work with the government and local communities on social programs.

Due to the desired modifications to the processing plant and infrastructure locations, a Modified Environmental Impact Study is required. B2Gold has commenced work on the modifications to the Environmental Impact Study and expect it to be completed and submitted shortly following the completion of the feasibility study. If the final economics of the feasibility study are positive and B2Gold makes the decision to develop the Gramalote Project as an open pit gold mine, B2Gold would utilize its proven internal mine construction team to build the mine and mill facilities.
17



LIQUIDITY AND CAPITAL RESOURCES
B2Gold continues to maintain a strong financial position and liquidity. At June 30, 2024, the Company had cash and cash equivalents of $467 million (December 31, 2023 - $307 million) and working capital (defined as current assets less assets classified as held for sale and current liabilities) of $600 million (December 31, 2023 - $397 million). At June 30, 2024, the full amount of the Company's $700 million RCF was undrawn and available.

In January 2024, to further enhance the financial flexibility of the Company and provide additional cash liquidity as the Company continues to fund sustaining, development and growth projects across the operating portfolio, and increase financial capacity for potential growth projects in Namibia and Colombia, B2Gold entered into a Gold Prepay with a number of its existing lenders. The Company received an upfront payment of $500 million, based on gold forward curve prices averaging approximately $2,191 per ounce, in exchange for equal monthly deliveries of gold from July 2025 to June 2026 totaling 264,768 ounces, representing approximately 12% of expected annual gold production in each of 2025 and 2026 (subject to finalization of production guidance for 2025 and 2026). Gold deliveries can be from production from any of the Company’s operating mines and the Gold Prepay can be settled prior to maturity through accelerated delivery of the remaining deliverable gold ounces. The Gold Prepay was executed by Bank of Montreal, Canadian Imperial Bank of Commerce, ING Capital Markets LLC, and National Bank of Canada. In the first quarter of 2024, the Company utilized a portion of the proceeds from the $500 million Gold Prepay completed in January 2024 to repay the $150 million balance drawn on the RCF, leaving the full amount of $700 million available for future draw downs.

The Company has a RCF with a syndicate of international banks for an aggregate amount of $700 million. The RCF also allows for an accordion feature whereby upon receipt of additional binding commitments, the facility may be increased to $800 million any time prior to the maturity date of December 16, 2025. The RCF bears interest on a sliding scale of between the Secured Overnight Financing Rate (“SOFR”) plus a term credit spread adjustment in addition to the existing sliding scale premium of between 2.00% to 2.50%. Commitment fees for the undrawn portion of the facility are also on a sliding scale basis of between 0.45% and 0.563%. The Company has provided security on the RCF in the form of a general security interest over the Company’s assets and pledges creating a charge over the shares of certain of the Company’s direct and indirect subsidiaries. In connection with the RCF, the Company must also maintain certain ratios for leverage and interest coverage. As at June 30, 2024, the Company was in compliance with these debt covenants.

The Company has a gold stream arrangement with Wheaton Precious Metals Corp. with a deposit amount of $84 million. The delivery obligation is as follows:

2.7805% of gold production up to delivery of 87,100 oz;
1.4405% of gold production up to an aggregate of 134,000 oz; and
1.005% of gold production thereafter.

The Company has guaranteed the remaining portion of the gold stream obligation.

For the second quarter of 2024, capital expenditures totalled $219 million. The most significant capital expenditures were on the Fekola Mine with capital expenditures of $53 million, the Masbate Mine had capital expenditures of $7 million, the Otjikoto Mine had capital expenditures of $12 million, the Goose Project had capital expenditures of $128 million, the Gramalote Project had capital expenditures of $4 million and the Fekola Regional properties had capital expenditures of $5 million. Other exploration costs for the second quarter of 2024 totalled $12 million. For the first half of 2024, capital expenditures totalled $456 million. The most significant capital expenditures were Fekola Mine expenditures of $134 million, Masbate Mine expenditures of $15 million, Otjikoto Mine expenditures of $26 million, Goose Project expenditures of $245 million, Gramalote Project expenditures of $7 million, and Fekola Regional expenditures of $9 million. Other exploration costs for the first half of 2024 totalled $20 million.

18



As at June 30, 2024, the Company had the following commitments (in addition to those disclosed elsewhere in the MD&A):

For payments at the Fekola Mine of $17 million related to underground development, $13 million related to mobile purchases and rebuilds, $6 million related to the solar plant expansion, $3 million related to the construction of a new tailing storage facility, and $2 million related to plant and powerhouse maintenance. Of these amounts, $37 million is expected to be incurred in 2024 and the remaining $4 million in 2025.
For payments at the Goose Project of $43 million related to construction activities and $1 million related to mobile equipment, all of which is expected to be incurred in 2024.
For payments at the Masbate Mine of $1 million related to process plant equipment, all of which is expected to be incurred in 2024.

Derivative financial instruments

Forward contracts - fuel oil, gas oil, diesel
The Company uses forward contracts for fuel oil, gas oil and diesel to manage the risk of volatility in the Company's future operating costs. The Company reviews the open positions and the potential for additional forward contracts on an ongoing basis. During the six months ended June 30, 2024, the Company entered into additional series of forward contracts for the purchase of 27,177,000 litres of fuel oil and 40,546,000 litres of gas oil with scheduled settlement between July 2024 and April 2026. These derivative instruments were not designated as hedges by the Company and are being recorded at fair value through profit and loss ("FVTPL").
The following is a summary, by maturity dates, of the Company’s fuel derivative contracts outstanding as at June 30, 2024:
 202420252026Total
Forward – fuel oil: 
Litres (thousands)10,956 13,705 3,384 28,045 
Average strike price$0.47 $0.46 $0.43 $0.46 
Forward – gas oil:
Litres (thousands)12,792 22,271 5,483 40,546 
Average strike price$0.62 $0.62 $0.60 $0.62 
The unrealized fair value of these contracts at June 30, 2024 was $0.5 million.

Operating activities

Cash flow provided by operating activities was $62 million in the second quarter of 2024 compared to $195 million in the second quarter of 2023, a decrease of $133 million due mainly to higher working capital outflows, higher long-term value added tax receivables outflows and higher long-term inventory outflows, partially offset by higher revenues. Cash income and withholding tax payments in the second quarter of 2024 totalled $133 million (second quarter of 2023 - $59 million), including approximately $82 million related to 2023 outstanding tax liability obligations.

Cash flow provided by operating activities was $773 million in the first half of 2024 compared to $399 million in the first half of 2023, an increase of $374 million due mainly to $500 million of proceeds received from the Gold Prepay in January 2024, higher revenues, partially offset by higher production costs, higher working capital outflows and higher long-term inventory outflows. Cash income and withholding tax payments in the first half of 2024 totalled $172 million (first half of 2023 - $90 million), including approximately $88 million related to 2023 outstanding tax liability obligations. Based on actual results for the first quarter of 2024 and revised forecast assumptions, including an average forecast gold price of $2,150 per ounce for the balance of 2024 (previously $2,000 per ounce), the Company is now forecasting to make total cash income tax payments for current income tax, withholding and other taxes in 2024 of approximately $289 million (previous estimate was $270 million).

Financing activities

For the second quarter of 2024, the Company’s cash used by financing activities was a net outflow of $52 million. During the second quarter of 2024, the Company made dividend payments of $46 million, made equipment loan facility repayments of $4 million, and distributed $3 million to non-controlling interests. For the first half of 2024, the Company’s cash used by financing activities was a net outflow of $259 million. During the first half of 2024, the Company repaid the $150 million balance drawn on the RCF, made interest and commitment fee payments of $5 million, made dividend payments of $92 million, made equipment loan facility repayments of $6 million and distributed $7 million to non-controlling interests.

In the first half of 2024, the Board declared two quarterly cash dividends for the first and second quarters of 2024 of $0.04 per common share each (or an expected $0.16 per share on an annualized basis). The declaration and payment of future quarterly dividends remains at the discretion of the Board and will depend on the Company's financial results, cash requirements, future prospects and other factors deemed relevant by the Board.
19




The Company has a dividend reinvestment plan ("DRIP"). The DRIP provides B2Gold shareholders residing in Canada and the United States with the opportunity to have the cash dividends declared on all or some of their common shares automatically reinvested into Reinvestment Shares on an ongoing basis. Participation in the DRIP is optional and will not affect shareholders’ cash dividends unless they elect to participate in the DRIP. Dividends are only payable as and when declared by the Company’s Board of Directors. The benefits of enrolling in the DRIP include the convenience of automatic reinvestment of dividends into Reinvestment Shares; flexibility to enroll some or all common shares in the DRIP; and ability to acquire Reinvestment Shares without paying any brokerage fees. Participants in the DRIP will acquire Reinvestment Shares issued from a Treasury Purchase at a price equal to the volume weighted average price of the Company’s common shares on the Toronto Stock Exchange for the five consecutive trading days immediately preceding a dividend payment date, subject to a possible discount, in the Company’s sole discretion, of up to 5%. For the dividend declared on February 21, 2024 and May 7, 2024, a discount of 3% was offered.

This dividend is designated as an "eligible dividend" for the purposes of the Income Tax Act (Canada). Dividends paid by B2Gold to shareholders outside Canada (non-resident investors) will be subject to Canadian non-resident withholding taxes.

The declaration and payment of future dividends and the amount of any such dividends will be subject to the determination of the Board, in its sole and absolute discretion, taking into account, among other things, economic conditions, business performance, financial condition, growth plans, expected capital requirements, compliance with the Company's constating documents, all applicable laws, including the rules and policies of any applicable stock exchange, as well as any contractual restrictions on such dividends, including any agreements entered into with lenders to the Company, and any other factors that the Board deems appropriate at the relevant time. There can be no assurance that any dividends will be paid at the intended rate or at all in the future.

Investing activities

For the second quarter of 2024, the Company’s cash used by investing activities was a net outflow of $108 million. For the second quarter of 2024, capital expenditures totalled $219 million. The most significant capital expenditures were on the Fekola Mine with capital expenditures of $53 million, the Masbate Mine had capital expenditures of $7 million, the Otjikoto Mine had capital expenditures of $12 million, the Goose Project had capital expenditures of $128 million, the Gramalote Project had capital expenditures of $4 million and the Fekola Regional properties had capital expenditures of $5 million. Other exploration costs for the second quarter of 2024 totalled $12 million. In addition, for the second quarter of 2024, the Company received cash proceeds from the sale of the investment in associate of $100 million, received cash proceeds from the sale of long-term investments of $19 million, and purchased long-term investments for $6 million.

For the first half of 2024, the Company’s cash used by investing activities was a net outflow of $348 million. For the first half of 2024, capital expenditures totalled $456 million. The most significant capital expenditures were Fekola Mine expenditures of $134 million, Masbate Mine expenditures of $15 million, Otjikoto Mine expenditures of $26 million, Goose Project expenditures of $245 million, Gramalote Project expenditures of $7 million, and Fekola Regional expenditures of $9 million. Other exploration costs for the first half of 2024 totalled $20 million. In addition, for the first half of 2024, the Company received cash proceeds from the sale of the investment in associate of $100 million, received cash proceeds from the sale of long-term investments of $19 million, and purchase of a long-term investments for $6 million.

20



Exploration

Resource property expenditures on exploration are disclosed in the table below:

 For the three months ended
June 30, 2024
For the three months ended
June 30, 2023
For the six months ended
June 30, 2024
For the six months ended June 30, 2023
 $$$$
 (000’s)(000’s)(000’s)(000’s)
Fekola Mine, exploration838 — 2,140 1,706 
Masbate Mine, exploration928 1,008 1,749 1,967 
Otjikoto Mine, exploration1,514 996 3,303 1,490 
Goose Project, exploration7,038 2,048 9,350 2,048 
George Property, exploration 1,277 157 1,277 
Menankoto Property, exploration 7,593  10,629 
Dandoko Property, exploration 3,154 (20)6,627 
Bantako North Property, exploration 3,782  5,223 
Finland Properties, exploration715 1,721 2,108 3,992 
Bakolobi Property, exploration 2,088 344 3,268 
Other539 885 1,281 2,316 
 11,572 24,552 20,412 40,543 

B2Gold is planning another year of extensive exploration in 2024 with a budget of approximately $63 million. A significant focus will be exploration at the Back River Gold District, with the goal of enhancing and growing the significant resource base at the Goose Project and surrounding regional targets. In Namibia, the exploration program at the Otjikoto Mine will be the largest program since 2012. In Mali, the exploration program will be a more strategic search for near-mine, near-surface sources of additional sulphide-related gold mineralization. In the Philippines, the exploration program at Masbate will focus on converting inferred mineral resource areas and expanding the existing open pits. Early stage exploration programs will continue in the Philippines and Cote d’Ivoire in 2024. Finally, the Company will continue to search for new joint ventures and strategic investment opportunities, building on existing equity investments in Snowline Gold Corp. and AuMEGA Metals Ltd.

2024 Guidance for Canada

A total of $28 million is budgeted for exploration at the Back River Gold District in 2024. A total of 25,000 metres of drilling will include some infill drilling in selected areas and target extensions of the Llama and Umwelt deposits, the largest and highest grade resources at the Goose Project. In addition to drilling, deep-imaging geophysical methods are planned in order to improve the Company’s ability to target new underground resources in areas such as Nuvuyak, Goose Neck and Kogoyak. Regional exploration including geophysics, mapping, and potentially, limited drilling will be undertaken on the George, Boot, Boulder and Del projects.

2024 Guidance for Mali

A total of $10 million is budgeted for exploration in Mali in 2024 with an ongoing focus on discovery of additional high-grade,
sulphide mineralization across the Fekola Complex to supplement feed to the Fekola mill. A total of 20,000 metres of diamond
and reverse circulation drilling is planned for 2024.

2024 Guidance for the Philippines

The total budget for the Philippines in 2024 is approximately $6 million, of which the Masbate exploration budget is $4 million, including approximately 7,000 metres of drilling. The 2024 exploration program will focus on drilling several greenfields targets between 3 kilometers and 12 kilometers south of the Masbate Mine infrastructure.

An additional $2 million will be allocated to targeting new regional projects in highly prospective areas in the Philippines, leveraging off B2Gold’s presence and operational experience in the country. A total of 4,000 metres is allocated to testing new
projects.

21



2024 Guidance for Namibia

A total of $9 million is budgeted for exploration at Otjikoto in 2024, the largest program since the definition of the Wolfshag discovery in 2012. The focus of the exploration program will be drilling the recently discovered Antelope deposit, located approximately 3 km south of Phase 5 of the Otjikoto open pit, with a total of 39,000 metres of drilling planned. The Antelope deposit, comprised of the Springbok Zone, the Oryx Zone, and a possible third structure, Impala, subject to confirmatory drilling, was discovered in 2022 following deep drill testing by B2Gold exploration personnel on three-dimensional models of airborne magnetic data.

On June 20, 2024, the Company announced an initial Inferred Mineral Resource estimate for the Springbok Zone, the southernmost shoot of the recently discovered Antelope deposit. Over 36,000 metres have been drilled into the Springbok Zone to date, with 33 holes totaling 16,950 metres completed in 2024, to establish the 50 x 50 metre spacing that informs this initial Inferred Mineral Resource estimate. Recent drilling at the Springbok Zone remains open to the south, indicating additional exploration potential beyond the currently defined resource.

The Company determined that the initial Inferred Mineral Resource estimate of 1.75 million tonnes grading 6.91 g/t gold for a total of 390,000 ounces of gold ounces was sufficient to initiate a PEA of development of the deposit by underground mining methods, similar to the Wolfshag deposit. Ongoing exploration drilling on the Oryx Zone, which appears to represent a second shoot northeast of and stacked stratigraphically above the Springbok Zone, has returned high-grade intervals that demonstrate the potential to increase the Mineral Resource estimate. Subject to receipt of a positive PEA study and permit, mining of the Springbok Zone, coupled with the exploration potential of the greater Antelope deposit, could begin to contribute to gold production at Otjikoto in 2026. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that these Inferred Mineral Resources will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

2024 Guidance for Greenfields Exploration

B2Gold has allocated approximately $13 million (including $2 million for the grassroots projects in the Philippines) in 2024 for its grassroots exploration programs, including Finland and Cote d’Ivoire.

In Finland, the Company had allocated $4 million to fund its 70% contribution to the Central Lapland Joint Venture with Aurion Resources Ltd ("Aurion"). A total of 9,700 metres of diamond drilling will test targets defined during an extensive prospectivity analysis completed in 2023.

A budget of approximately $3 million has been allocated by the Company for ongoing exploration in Cote d’Ivoire. A total of 17,000 metres of diamond, reverse circulation and reconnaissance auger drilling is planned in 2024.

In addition to the defined programs noted above, the Company has allocated approximately $4 million for the generation and evaluation of new greenfields targets.
CRITICAL ACCOUNTING ESTIMATES
Full disclosure of the Company’s accounting policies and significant accounting judgments and estimation uncertainties in accordance with IFRS can be found in Notes 4 and 5 of its Notes to the annual consolidated financial statements for the year ended December 31, 2023. Management considers the following estimates to be the most critical in understanding the judgments involved in preparing the Company’s interim consolidated financial statements and the uncertainties that could impact its results of operations, financial condition and cash flows:
Mineral reserve and resource estimates
Mineral reserves are estimates of the amount of ore that can be economically and legally extracted from the Company’s mining properties. The Company estimates its mineral reserves and mineral resources based on information compiled by appropriately qualified persons relating to the geological data on the size, depth and shape of the ore body, and requires complex geological assessments to interpret the data. The estimation of recoverable mineral reserves is based upon factors such as estimates of foreign exchange rates, commodity prices, future capital requirements, metallurgical recoveries, permitting and production costs along with geological assumptions made in estimating the size, and grade of the ore body. Changes in the mineral reserve or mineral resource estimates may impact the carrying value of mining interests, mine restoration provisions, the gold stream obligation, recognition of deferred tax assets, depreciation and amortization charges and royalties receivable.
Assessment of impairment and reversal of impairment indicators for long-lived assets
The Company applies significant judgement in assessing whether there are indicators of impairment or impairment reversal present that give rise to the requirement to conduct an impairment test. Internal and external factors such as significant changes in the use of the asset, legal and permitting factors, future gold prices, operating and capital cost forecasts, quantities of mineral reserves and resources, and movements in market interest rates are used by management in determining whether there are any indicators.
22




During the three months ended June 30, 2024, the Company identified changes to the indicators of impairment on the Fekola Complex cash-generating unit ("CGU"), consisting of the Fekola Mine and Fekola Regional Properties. As a result, these assets were tested for impairment.
Impairment of long-lived assets
Long-lived assets are tested for impairment, or reversal of a previous impairment, if there is an indicator of impairment or a subsequent reversal. Calculating the estimated recoverable amount of CGUs for long-lived asset requires management to make estimates and assumptions that include such factors as mineable mineralization including reserves and resources, future production levels, operating and capital costs, application of royalty, income tax and mining tax rates, future metal prices and discount rates. Changes in any of these assumptions or estimates used in determining the recoverable amount could impact the analysis. Such changes could be material.
Fekola Complex cash-generating unit
During the year ended December 31, 2023, the State of Mali ("the State") introduced a new mining code (the “2023 Mining Code”) and related Local Content Law. In July 2024, the accompanying Implementation Decrees which clarify how the provisions of the 2023 Mining Code and Local Content Law should be applied were enacted into law. The Company and the State remain in ongoing negotiations related to how certain components of the 2023 Mining Code should be applied to the Fekola Complex. The final outcomes of these discussions cannot yet be determined.
For the year ended December 31, 2023, the Company recorded an impairment of $206 million for the Fekola Complex. The known and estimated changes to the financial framework of the Fekola Complex as impacted by the 2023 Mining Code and the ongoing discussions with the State are considered to be updated indicators of impairment for the Fekola Complex assets.
As a result, the Company has performed an updated impairment assessment on the Fekola Complex CGU. The carrying value of the CGU was compared to the CGU’s recoverable amount which was determined to be its fair value less costs of disposal ("FVLCD"). To estimate the recoverable amount of the CGU for impairment, the Company utilized a discounted cash flow model incorporating significant assumptions that included such factors as mineable mineralization including reserves and resources, future production levels, operating and capital costs, fuel taxes and the expected application of revised royalty and revenue based tax rates, forecast annual gold prices per ounce of $2,222 (2024), $2,231 (2025), $2,150 (2026), $2,055 (2027), long-term gold price of $1,900 per ounce thereafter, and a discount rate of 7.5% for the Fekola Complex. Management’s estimate of the FVLCD of its CGU is classified as level 3 in the fair value hierarchy. The Company’s estimate of future cash flows is subject to risks and uncertainties and therefore could change in the future if the underlying assumptions change.
The Company’s analysis concluded that the Fekola Complex CGU was impaired resulting in an impairment of $215 million. A net impairment charge of $194 million after taking into account a deferred income tax recovery of $21 million was recorded in the Condensed Interim Consolidated Statement of Operations for the six month period ended June 30, 2024.
The recoverable amount of the Fekola Complex CGU is most sensitive to changes in the gold price and discount rate. In isolation, a $50 per ounce decrease in the gold price would result in a reduction in the recoverable amount of the Fekola Complex CGU of approximately $96 million. In isolation, a 25 basis point increase in the discount rate would result in a reduction in the recoverable amount of the Fekola Complex CGU of approximately $12 million.
In addition, based on the current status of discussions with the State, the Company has recorded additional tax provisions of $37 million in the quarter ended June 30, 2024 for the expected settlement of income tax audits and assessments up to the balance sheet date.
Fair value of financial instruments
The fair value of financial instruments that are not traded in an active market are determined using valuation techniques. In determining the fair value of the gold stream obligation, the Company makes significant assumptions that are based on the underlying models and the market conditions existing at both initial recognition and the end of each reporting period.
Value-added tax receivables

The Company incurs indirect taxes, including value-added tax, on purchases of goods and services at its operating mines and development projects. Indirect tax balances are recorded at their estimated recoverable amounts within current or long-term assets, net of provisions, and reflect the Company’s best estimate of their recoverability under existing tax rules in the respective jurisdictions in which they arise. Management’s assessment of recoverability considers the probable outcomes of claimed deductions and/or disputes. The provisions and balance sheet classifications made to date may be subject to change and such change may be material.
23




Long-term value-added tax receivables at June 30, 2024 includes amounts for the Fekola Mine of $183 million (December 31, 2023 - $137 million), for the Masbate Mine of $50 million (December 31, 2023 – $45 million), and for the Gramalote Project of $17 million (December 31, 2023 - $18 million).

Uncertain tax positions
The Company’s operations involve the application of complex tax regulations in multiple international jurisdictions. Determining the tax treatment of a transaction requires the Company to apply judgement in its interpretation of the applicable tax law. These positions are not final until accepted by the relevant tax authority. The tax treatment may change based on the result of assessments or audits by the tax authorities often years after the initial filing.

The Company recognizes and records potential liabilities for uncertain tax positions based on its assessment of the amount, or range of amounts, of tax that will be due. The Company adjusts these accruals as new information becomes available. Due to the complexity and uncertainty associated with certain tax treatments, the ultimate resolution could result in a payment that is materially different from the Company’s current estimate of the tax liabilities.

Current and deferred income taxes

The Company is periodically required to estimate the tax basis of assets and liabilities. Where applicable tax laws and regulations are either unclear or subject to varying interpretations, it is possible that changes in these estimates could occur that materially affect the amounts of deferred income tax assets and liabilities recorded in the financial statements. Changes in deferred tax assets and liabilities generally have a direct impact on earnings in the period that the changes occur.

Each period, the Company evaluates the likelihood of whether some portion or all of each deferred tax asset will not be realized. This evaluation is based on historic and future expected levels of taxable income and the associated repatriation of retained earnings, the pattern and timing of reversals of taxable temporary timing differences that give rise to deferred tax liabilities, and tax planning initiatives. Levels of future taxable income are affected by, among other things, metal prices, production costs, quantities of proven and probable gold reserves, interest rates and foreign currency exchange rates. The availability of retained earnings for distribution depends on future levels of taxable income as well as future reclamation expenditures, capital expenditures, dividends and other uses of available cash flow.
RISKS AND UNCERTAINTIES
The exploration and development of natural resources are highly speculative in nature and the Company’s business operations, investments and prospects are subject to significant risks. For details of these risks, please refer to the risk factors set forth in the Company’s current Annual Information Form, which can be found under the Company’s corporate profile on SEDAR+ at www.sedarplus.ca, the Company’s current Form 40-F Annual Report, which can be found on EDGAR at www.sec.gov, and the Company’s other filings and submissions with securities regulators on SEDAR+ and EDGAR, which could materially affect the Company’s business, operations, investments and prospects and could cause actual events to differ materially from those described in forward-looking statements relating to the Company. Additional risks and uncertainties not presently known to the Company or that the Company currently considers immaterial may also impair the business, operations, investments and prospects of the Company. If any of the risks actually occur, the business of the Company may be negatively impacted and its financial condition and results of operations may suffer significantly.
INTERNAL CONTROL OVER FINANCIAL REPORTING
The Company’s management, with the participation of the Company’s Chief Executive Officer and Chief Financial Officer, are responsible for establishing and maintaining adequate internal control over financial reporting. The Company’s internal control over financial reporting is a process designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with IFRS. Any system of internal control over financial reporting, no matter how well designed, has inherent limitations. As a result, even those systems determined to be effective can only provide reasonable assurance regarding the preparation of financial statements.
The Company’s management has determined that there have been no significant changes in the Company’s internal control over financial reporting during the three months ended June 30, 2024, that have materially affected, or are reasonably likely to materially affect, the Company’s internal control over financial reporting.
24



NON-IFRS MEASURES
Cash operating costs per gold ounce sold and total cash costs per gold ounce sold
‘‘Cash operating costs per gold ounce’’ and “total cash costs per gold ounce” are common financial performance measures in the gold mining industry but, as non-IFRS measures, they do not have a standardized meaning under IFRS and therefore may not be comparable to similar measures presented by other issuers. Management believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate our performance and ability to generate cash flow. Accordingly, these measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measures, along with sales, are considered to be a key indicator of the Company’s ability to generate earnings and cash flow from its mining operations.
Cash cost figures are calculated on a sales basis in accordance with a standard developed by The Gold Institute, which was a worldwide association of suppliers of gold and gold products and included leading North American gold producers. The Gold Institute ceased operations in 2002, but the standard is the accepted standard of reporting cash cost of production in North America. Adoption of the standard is voluntary and the cost measures presented may not be comparable to other similarly titled measures of other companies. Other companies may calculate these measures differently. Cash operating costs and total cash costs per gold ounce sold are derived from amounts included in the statement of operations and include mine site operating costs such as mining, processing, smelting, refining, transportation costs, royalties and production taxes, less silver by-product credits. The tables below show a reconciliation of cash operating costs per gold ounce sold and total cash costs per gold ounce sold to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis (dollars in thousands):


For the three months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs81,481 37,602 32,216 151,299 13,221 164,520 
Royalties and production taxes21,655 6,910 4,524 33,089 711 33,800 
Total cash costs103,136 44,512 36,740 184,388 13,932 198,320 
Gold sold (ounces)115,288 46,600 48,340 210,228 8,267 218,495 
Cash operating costs per ounce ($/ gold ounce sold)707 807 666 720 1,599 753 
Total cash costs per ounce ($/ gold ounce sold)895 955 760 877 1,685 908 
For the three months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs79,245 48,170 25,347 152,762 17,815 170,577 
Royalties and production taxes23,686 6,285 3,140 33,111 1,078 34,189 
Total cash costs102,931 54,455 28,487 185,873 18,893 204,766 
Gold sold (ounces)142,850 56,700 39,550 239,100 16,797 255,897 
Cash operating costs per ounce ($/ gold ounce sold)555 850 641 639 1,061 667 
Total cash costs per ounce ($/ gold ounce sold)721 960 720 777 1,125 800 
25




For the six months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs166,586 80,373 61,085 308,044 25,126 333,170 
Royalties and production taxes42,050 12,300 8,766 63,116 1,565 64,681 
Total cash costs208,636 92,673 69,851 371,160 26,691 397,851 
Gold sold (ounces)239,116 94,300 99,790 433,206 19,644 452,850 
Cash operating costs per ounce ($/ gold ounce sold)697 852 612 711 1,279 736 
Total cash costs per ounce ($/ gold ounce sold)873 983 700 857 1,359 879 
For the six months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs156,906 73,163 50,297 280,366 33,580 313,946 
Royalties and production taxes50,352 10,698 7,222 68,272 2,332 70,604 
Total cash costs207,258 83,861 57,519 348,638 35,912 384,550 
Gold sold (ounces)307,900 86,350 94,000 488,250 32,939 521,189 
Cash operating costs per ounce ($/ gold ounce sold)510 847 535 574 1,019 602 
Total cash costs per ounce ($/ gold ounce sold)673 971 612 714 1,090 738 
Cash operating costs per gold ounce produced
In addition to cash operating costs on a per gold ounce sold basis, the Company also presents cash operating costs on a per gold ounce produced basis. Cash operating costs per gold ounce produced is derived from amounts included in the statement of operations and include mine site operating costs such as mining, processing, smelting, refining, transportation costs, less silver by-product credits. The tables below show a reconciliation of cash operating costs per gold ounce produced to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis (dollars in thousands):
26



For the three months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs81,481 37,602 32,216 151,299 13,221 164,520 
Inventory sales adjustment 12,097 1,412 168 13,677 — 13,677 
Cash operating costs93,578 39,014 32,384 164,976 13,221 178,197 
Gold produced (ounces)111,583 44,515 48,143 204,241 8,267 212,508 
Cash operating costs per ounce ($/ gold ounce produced)839 876 673 808 1,599 839 
For the three months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs79,245 48,170 25,347 152,762 17,815 170,577 
Inventory sales adjustment 2,698 (7,757)1,587 (3,472)— (3,472)
Cash operating costs81,943 40,413 26,934 149,290 17,815 167,105 
Gold produced (ounces)152,427 49,478 44,056 245,961 16,740 262,701 
Cash operating costs per ounce ($/ gold ounce produced)538 817 611 607 1,064 636 
For the six months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs166,586 80,373 61,085 308,044 25,126 333,170 
Inventory sales adjustment 10,175 188 440 10,803 — 10,803 
Cash operating costs176,761 80,561 61,525 318,847 25,126 343,973 
Gold produced (ounces)230,724 94,297 93,559 418,580 19,644 438,224 
Cash operating costs per ounce ($/ gold ounce produced)766 854 658 762 1,279 785 
27



For the six months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Production costs156,906 73,163 50,297 280,366 33,580 313,946 
Inventory sales adjustment 5,216 8,180 (62)13,334 — 13,334 
Cash operating costs162,122 81,343 50,235 293,700 33,580 327,280 
Gold produced (ounces)318,291 95,842 82,547 496,680 32,877 529,557 
Cash operating costs per ounce ($/ gold ounce produced)509 849 609 591 1,021 618 
All-in sustaining costs per gold ounce
In June 2013, the World Gold Council, a non-regulatory association of the world’s leading gold mining companies established to promote the use of gold to industry, consumers and investors, provided guidance for the calculation of the measure “all-in sustaining costs per gold ounce”, but as a non-IFRS measure, it does not have a standardized meaning under IFRS and therefore may not be comparable to similar measures presented by other issuers. The original World Gold Council standard became effective January 1, 2014 with further updates announced on November 16, 2018 which were effective starting January 1, 2019.
Management believes that the all-in sustaining costs per gold ounce measure provides additional insight into the costs of producing gold by capturing all of the expenditures required for the discovery, development and sustaining of gold production and allows the Company to assess its ability to support capital expenditures to sustain future production from the generation of operating cash flows. Management believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company's performance and ability to generate cash flow. Accordingly, it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Adoption of the standard is voluntary and the cost measures presented may not be comparable to other similarly titled measures of other companies. The Company has applied the principles of the World Gold Council recommendations and has reported all-in sustaining costs on a sales basis. Other companies may calculate these measures differently.
B2Gold defines all-in sustaining costs per ounce as the sum of cash operating costs, royalties and production taxes, capital expenditures and exploration costs that are sustaining in nature, sustaining lease expenditures, corporate general and administrative costs, share-based payment expenses related to restricted share units/deferred share units/performance share units/restricted phantom units ("RSUs/DSUs/PSUs/RPUs"), community relations expenditures, reclamation liability accretion and realized (gains) losses on fuel derivative contracts, all divided by the total gold ounces sold to arrive at a per ounce figure.
28



The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the three months ended June 30, 2024 (dollars in thousands):
For the three months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotalCalibre equity investmentGrand
Total
$$$$$$$
Production costs81,481 37,602 32,216 — 151,299 13,221 164,520 
Royalties and production taxes21,655 6,910 4,524 — 33,089 711 33,800 
Corporate administration2,548 548 1,406 8,466 12,968 902 13,870 
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)
34 — — 4,023 4,057 — 4,057 
Community relations 106 17 319 — 442 — 442 
Reclamation liability accretion
458 313 252 — 1,023 — 1,023 
Realized gains on derivative contracts(202)(108)— — (310)— (310)
Sustaining lease expenditures83 309 236 512 1,140 — 1,140 
Sustaining capital expenditures(2)
38,065 6,428 11,605 — 56,098 637 56,735 
Sustaining mine exploration(2)
838 864 (76)— 1,626 — 1,626 
Total all-in sustaining costs145,066 52,883 50,482 13,001 261,432 15,471 276,903 
Gold sold (ounces)115,288 46,600 48,340 — 210,228 8,267 218,495 
All-in sustaining cost per ounce ($/ gold ounce sold)1,258 1,135 1,044 — 1,244 1,871 1,267 
(1) Included as a component of Share-based payments on the Statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below.

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2024 (dollars in thousands):
For the three months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Operating mine capital expenditures53,179 6,507 11,706 71,392 637 72,029 
Fekola underground(14,772)— — (14,772)— (14,772)
Road construction(342)— — (342)— (342)
Land acquisitions— (49)— (49)— (49)
Other— (30)(101)(131)— (131)
Sustaining capital expenditures38,065 6,428 11,605 56,098 637 56,735 

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2024 (dollars in thousands):
For the three months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total Calibre equity investmentGrand
Total
$$$$$$
Operating mine exploration838 928 1,514 3,280 — 3,280 
Regional exploration— (64)(1,590)(1,654)— (1,654)
Sustaining mine exploration838 864 (76)1,626 — 1,626 
29



The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the three months ended June 30, 2023 (dollars in thousands):
For the three months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotalCalibre equity investmentGrand
Total
$$$$$$$
Production costs79,245 48,170 25,347 — 152,762 17,815 170,577 
Royalties and production taxes23,686 6,285 3,140 — 33,111 1,078 34,189 
Corporate administration2,403 640 1,176 9,836 14,055 574 14,629 
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)
— — — 3,838 3,838 — 3,838 
Community relations 1,370 41 311 — 1,722 — 1,722 
Reclamation liability accretion
357 278 277 — 912 — 912 
Realized gains on derivative contracts(688)(642)(209)— (1,539)— (1,539)
Sustaining lease expenditures981 303 297 465 2,046 — 2,046 
Sustaining capital expenditures(2)
59,032 5,752 15,630 — 80,414 1,933 82,347 
Sustaining mine exploration(2)
— 1,008 996 — 2,004 — 2,004 
Total all-in sustaining costs166,386 61,835 46,965 14,139 289,325 21,400 310,725 
Gold sold (ounces)142,850 56,700 39,550 — 239,100 16,797 255,897 
All-in sustaining cost per ounce ($/ gold ounce sold)1,165 1,091 1,187 — 1,210 1,274 1,214 
(1) Included as a component of Share-based payments on the Statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2023 (dollars in thousands):
For the three months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total Calibre equity investmentGrand
Total
$$$$$$
Operating mine capital expenditures74,151 6,098 15,630 95,879 1,933 97,812 
Road construction(2,657)— — (2,657)— (2,657)
Fekola underground(12,462)— — (12,462)— (12,462)
Other— (346)— (346)— (346)
Sustaining capital expenditures59,032 5,752 15,630 80,414 1,933 82,347 

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2023 (dollars in thousands):
For the three months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Operating mine exploration— 1,008 996 2,004 — 2,004 
Regional exploration— — —  —  
Sustaining mine exploration— 1,008 996 2,004 — 2,004 

30



The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the six months ended June 30, 2024 (dollars in thousands):
For the six months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotalCalibre equity investmentGrand
Total
$$$$$$$
Production costs166,586 80,373 61,085 — 308,044 25,126 333,170 
Royalties and production taxes42,050 12,300 8,766 — 63,116 1,565 64,681 
Corporate administration5,275 1,062 2,886 17,883 27,106 1,463 28,569 
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)
67 — — 8,996 9,063 — 9,063 
Community relations 251 30 650 — 931 — 931 
Reclamation liability accretion
893 614 490 — 1,997 — 1,997 
Realized gains on derivative contracts(420)(252)(31)— (703)— (703)
Sustaining lease expenditures167 627 790 1,004 2,588 — 2,588 
Sustaining capital expenditures(2)
105,935 14,677 24,503 — 145,115 2,392 147,507 
Sustaining mine exploration(2)
2,140 1,598 626 — 4,364 — 4,364 
Total all-in sustaining costs322,944 111,029 99,765 27,883 561,621 30,546 592,167 
Gold sold (ounces)239,116 94,300 99,790 — 433,206 19,644 452,850 
All-in sustaining cost per ounce ($/ gold ounce sold)1,351 1,177 1,000 — 1,296 1,555 1,308 
(1) Included as a component of Share-based payments on the Statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below.

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2024 (dollars in thousands):
For the six months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Operating mine capital expenditures133,741 15,037 25,519 174,297 2,392 176,689 
Fekola underground(25,876)— — (25,876)— (25,876)
Road construction(1,930)— — (1,930)— (1,930)
Land acquisitions— (120)— (120)— (120)
Other— (240)(1,016)(1,256)— (1,256)
Sustaining capital expenditures105,935 14,677 24,503 145,115 2,392 147,507 

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2024 (dollars in thousands):
For the six months ended June 30, 2024
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total Calibre equity investmentGrand
Total
$$$$$$
Operating mine exploration2,140 1,749 3,303 7,192 — 7,192 
Regional exploration— (151)(2,677)(2,828)— (2,828)
Sustaining mine exploration2,140 1,598 626 4,364 — 4,364 
31



The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the six months ended June 30, 2023 (dollars in thousands):
For the six months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotalCalibre equity investmentGrand
Total
$$$$$$$
Production costs156,906 73,163 50,297 — 280,366 33,580 313,946 
Royalties and production taxes50,352 10,698 7,222 — 68,272 2,332 70,604 
Corporate administration5,364 1,139 2,880 18,857 28,240 1,323 29,563 
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)
— — — 8,157 8,157 — 8,157 
Community relations 2,044 99 582 — 2,725 — 2,725 
Reclamation liability accretion
738 569 571 — 1,878 — 1,878 
Realized gains on derivative contracts(1,459)(1,814)(697)— (3,970)— (3,970)
Sustaining lease expenditures1,045 610 920 914 3,489 — 3,489 
Sustaining capital expenditures(2)
108,808 14,528 32,976 — 156,312 3,939 160,251 
Sustaining mine exploration(2)
1,706 1,967 1,490 — 5,163 — 5,163 
Total all-in sustaining costs325,504 100,959 96,241 27,928 550,632 41,174 591,806 
Gold sold (ounces)307,900 86,350 94,000 — 488,250 32,939 521,189 
All-in sustaining cost per ounce ($/ gold ounce sold)1,057 1,169 1,024 — 1,128 1,250 1,135 
(1) Included as a component of Share-based payments on the Statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2023 (dollars in thousands):
For the six months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total Calibre equity investmentGrand
Total
$$$$$$
Operating mine capital expenditures127,946 15,051 32,976 175,973 3,939 179,912 
Road construction(5,067)— — (5,067)— (5,067)
Fekola underground study(14,071)— — (14,071)— (14,071)
Other— (523)— (523)— (523)
Sustaining capital expenditures108,808 14,528 32,976 156,312 3,939 160,251 

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2023 (dollars in thousands):
For the six months ended June 30, 2023
Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity investmentGrand
Total
$$$$$$
Operating mine exploration1,706 1,967 1,490 5,163 — 5,163 
Regional exploration— — —  —  
Sustaining mine exploration1,706 1,967 1,490 5,163 — 5,163 

32



Adjusted net income and adjusted earnings per share - basic
Adjusted net income and adjusted earnings per share – basic are non-IFRS measures that do not have a standardized meaning prescribed by IFRS and therefore may not be comparable to similar measures presented by other issuers. The Company defines adjusted net income as net income attributable to shareholders of the Company adjusted for non-recurring items and also significant recurring non-cash items. The Company defines adjusted earnings per share – basic as adjusted net income divided by the basic weighted number of common shares outstanding.
Management believes that the presentation of adjusted net income and adjusted earnings per share - basic is appropriate to provide additional information to investors regarding items that we do not expect to continue at the same level in the future or that management does not believe to be a reflection of the Company's ongoing operating performance. Management further believes that its presentation of these non-IFRS financial measures provide information that is useful to investors because they are important indicators of the strength of our operations and the performance of our core business. Accordingly, it is intended to provide additional information and should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS. Other companies may calculate this measure differently.
A reconciliation of net income to adjusted net income as extracted from the unaudited condensed interim consolidated financial statements is set out in the table below:
 Three months endedSix months ended
 June 30,June 30,
 2024202320242023
 $$$$
 (000’s)(000’s)(000’s)(000’s)
Net (loss) income attributable to shareholders of the Company for the period:(24,004)80,418 15,747 166,391 
Adjustments for non-recurring and significant recurring non-cash items:
Impairment of long-lived assets197,141 4,885 197,141 4,885 
Write-down of mining interests636 — 636 16,419 
Gain on sale of shares in associate(16,822)— (16,822)— 
Gain on sale of mining interests(48,662)— (48,662)— 
Unrealized (gains) losses on derivative instruments(119)757 (1)3,545 
Office lease termination costs —  1,946 
Loan receivable provision 2,085  2,085 
Change in fair value of gold stream8,387 1,100 19,239 1,100 
(Gain) loss on dilution of associate(998)— 8,984 — 
Deferred income tax recovery(37,110)(3,441)(16,310)(4,705)
Adjusted net income attributable to shareholders of the Company for the period78,449 85,804 159,952 191,666 
Basic weighted average number of common shares outstanding (in thousands)1,307,176 1,251,832 1,305,183 1,164,104 
Adjusted net earnings attributable to shareholders of the Company per share–basic ($/share)0.06 0.07 0.12 0.16 

33



SUMMARY OF QUARTERLY RESULTS
 Q2Q1Q4Q3Q2Q1Q4Q3
 20242024202320232023202320222022
Gold revenue ($ in thousands)492,569461,444511,974477,888470,854473,556592,468392,554
Net (loss) income for the period ($ in thousands)
(34,777)48,481(117,396)(34,770)91,850101,904176,468(21,234)
(Loss) earnings per share (1) – basic ($)
(0.02)0.03(0.09)(0.03)0.060.080.15(0.02)
(Loss) earnings per share (1) – diluted ($)
(0.02)0.03(0.09)(0.03)0.060.080.15(0.02)
Cash flows provided by operating activities ($ in thousands)
62,432710,727205,443110,204194,983203,823270,49193,118
Gold sold (ounces)
210,228222,978256,921248,889239,100249,150339,355229,400
Average realized gold price ($/ ounce)
2,3432,0691,9931,9201,9691,9011,7461,711
Gold produced (ounces)
204,241214,339270,611225,052245,961250,719352,769214,903
Gold produced, total including Calibre equity investment (ounces)
212,508225,716288,665242,838262,701266,856367,870227,016
Production costs ($ in thousands)151,299156,745164,406171,425152,762127,604159,559185,704
Cash operating costs (2) ($/ gold ounce sold)
753720661706667540497824
Total cash costs (2) ($/ gold ounce sold)
908851786840800678618939
All-in sustaining costs (2) ($/ gold ounce sold)
1,2671,3451,2571,2721,2141,0608921,169
Adjusted net income (1)(2) ($ in thousands)
78,44981,50390,69764,84085,804105,862121,44231,996
Adjusted earnings per share (1)(2) – basic ($)
0.060.060.070.050.070.100.110.03
(1) Attributable to the shareholders of the Company.
(2) Non-IFRS Measure. For a description of how these measures are calculated and a reconciliation of these measures to the most directly comparable measures specified, defined or determined under IFRS and presented in the Company’s financial statements, refer to “Non-IFRS Measures”.

Quarterly gold revenue throughout the eight quarters is a function of quarterly production levels, the timing of bullion shipments and changes in average realized gold price while cash flows from operating activities are also impacted by cash operating costs of each quarter and changes in working capital, in addition to the factors noted for gold revenue. Net income throughout the eight quarters is a function of quarterly revenues, cash operating costs, related taxes and asset impairment charges. The net loss in the third quarter of 2023 reflects an impairment loss of $112 million impairment charge on the Gramalote Project as a result of the Company's acquisition from AngloGold of the remaining 50% stake in the Gramalote Project. The net loss in the fourth quarter of 2023 reflects an impairment of $192 million related to the Fekola Complex, net of deferred income tax. The net loss in the second quarter of 2024 reflects an impairment of $194 million related to the Fekola Complex, net of deferred income tax, partially offset by a gain on sale of mining interests of $49 million and a gain on sale of shares in associate of $17 million.

SUMMARY AND OUTLOOK
Total gold production guidance for 2024 is forecast to be between 800,000 and 870,000 ounce, including 20,000 ounces of attributable production from Calibre.
Gold production in 2025 is expected to increase relative to 2024 and include production from the Fekola Complex, as a result of the scheduled mining and processing of higher-grade ore from the Fekola and Cardinal pits made accessible by the meaningful stripping campaign that will be undertaken throughout 2024, the expected full year contribution of higher-grade ore from Fekola Regional which is anticipated to contribute between 80,000 to 100,000 ounces of additional production, and commencement of mining the higher-grade Fekola underground (subject to receipt of necessary permits for Fekola Regional and Fekola underground).

Upon completion of construction activities at the Goose Project, the mine is expected to commence gold production in the second quarter of 2025 and contribute between 120,000 and 150,000 ounces of gold production in calendar year 2025. Over the first five full calendar years of operation from 2026 to 2030, the average annual gold production for the Goose Project is estimated to be in excess of 310,000 ounces of gold per year.

The positive PEA results on the Company’s 100% owned Gramalote Project, located in the Department of Antioquia, Colombia, outlines a significant production profile with average annual gold production of 234,000 ounces per year for the first five years of production, and strong project economics over a 12.5 year project life. As a result, B2Gold has commenced feasibility work with the goal of completing a feasibility study by mid-2025 and a $10 million budget has been approved by the Board.

Following the release of an initial Inferred Mineral Resource Estimate for the Springbok Zone, the southernmost shoot of the recently discovered Antelope deposit, located approximately three km south of the Otjikoto Phase 5 open pit at the Otjikoto Mine in Namibia, in the second quarter of 2024, the Company has commenced a PEA which is expected to be completed in the first
34



half of 2025. Subject to receipt of a positive PEA and permit, mining of the Springbok Zone, coupled with the exploration potential of the greater Antelope deposit, could begin to contribute to gold production at Otjikoto in 2026. The Antelope deposit has the potential to supplement the processing of low-grade stockpiles at the Otjikoto Mine through 2031, with the goal of increasing gold production levels to over 100,000 ounces per year from 2026 through 2031.

The Company's ongoing strategy is to continue to maximize profitable production from its existing mines, maintain a strong financial position, realize the potential increase in gold production from the Company’s existing development projects, continue exploration programs across the Company’s robust land packages, evaluate new exploration, development and production opportunities, and continue to return capital to shareholders.
OUTSTANDING SHARE DATA
At August 8, 2024, 1,310,797,910 common shares were outstanding. In addition, there were approximately 28 million stock options outstanding with exercise prices ranging between Cdn.$3.37 to Cdn.$8.53 per share, approximately 4.3 million RSUs outstanding and approximately 5.7 million PSUs outstanding.
CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
Production results and production guidance presented in this MD&A reflect the total production at the mines B2Gold operates on a 100% basis. Please see our most recent Annual Information Form for a discussion of our ownership interest in the mines B2Gold operates. In respect of Calibre’s operations, production is presented on an approximate 14% basis in the second quarter of 2024 until June 20, 2024 (to reflect B2Gold's approximate interest in Calibre during the period).

This MD&A includes certain “forward-looking information” and “forward-looking statements” (collectively “forward-looking statements”) within the meaning of applicable Canadian and United States securities legislation, including: projections; outlook; guidance; forecasts; estimates; and other statements regarding future or estimated financial and operational performance, gold production and sales, revenues and cash flows, and capital costs (sustaining and non-sustaining) and operating costs, including projected cash operating costs and all-in sustaining costs, and budgets on a consolidated and mine by mine basis, which if they occur, would have on our business, our planned capital and exploration expenditures; future or estimated mine life, metal price assumptions, ore grades or sources, gold recovery rates, stripping ratios, throughput, ore processing; statements regarding anticipated exploration, drilling, development, construction, permitting and other activities or achievements of B2Gold; and including, without limitation: remaining well positioned for continued strong operational and financial performance for 2024; projected gold production, cash operating costs and all-in sustaining costs on a consolidated and mine by mine basis in 2024; updated total consolidated gold production of between 800,000 and 870,000 ounces (including 20,000 attributable ounces from Calibre) in 2024, with cash operating costs of between $835 and $895 per ounce and all-in sustaining costs of between $1,420 and $1,480 per ounce; B2Gold’s continued prioritization of developing the Goose Project in a manner that recognizes Indigenous input and concerns and brings long-term socio-economic benefits to the area; the Goose Project capital cost being approximately C$1,050 million and the net cost of open pit and underground development, deferred stripping, and sustaining capital expenditures to be incurred prior to first gold production being approximately C$200 million and the cost for reagents and other working capital items being C$205 million; the Goose Project producing approximately 310,000 ounces of gold per year for the first five years; the Company's consolidated gold production to be relatively consistent throughout 2024; the potential for Fekola Regional to provide saprolite material to feed the Fekola mill within three months after receipt of an exploitation license; Fekola Regional production now expected to commence at the beginning of 2025; the impact of the 2023 mining code in Mali; the potential for completion of the mill construction in the first quarter of 2025 and first gold production in the second quarter of 2025 from the Goose Project; the potential to extend Wolfshag underground mine past 2026; the potential for the Antelope Zone to contribute to the Otjikoto production profile; the timing and results of a feasibility study for the Gramalote Project; the potential payment of future dividends, including the timing and amount of any such dividends, and the expectation that quarterly dividends will be maintained at the same level; and B2Gold's attributable share of Calibre’s operations. All statements in this MD&A that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as "expect", "plan", "anticipate", "project", "target", "potential", "schedule", "forecast", "budget", "estimate", "intend" or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made.

Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond B2Gold's control, including risks associated with or related to: the volatility of metal prices and B2Gold's common shares; changes in tax laws; the dangers inherent in exploration, development and mining activities; the uncertainty of reserve and resource estimates; not achieving production, cost or other estimates; actual production, development plans and costs differing materially from the estimates in B2Gold's feasibility and other studies; the ability to obtain and maintain any necessary permits, consents or authorizations required for mining activities; environmental regulations or hazards and compliance with complex regulations associated with mining activities; climate change and climate change regulations; the ability to replace mineral reserves and identify acquisition opportunities; the unknown liabilities of companies acquired by B2Gold; the ability to successfully integrate new acquisitions; fluctuations in exchange rates; the availability of financing; financing and debt activities, including potential restrictions imposed on B2Gold's operations as a result thereof and the ability to generate sufficient cash flows; operations in foreign and developing countries and the compliance with foreign laws, including those associated with operations in Mali, Namibia, the Philippines and Colombia and including risks related to changes in foreign laws and changing policies related to mining and local ownership requirements or resource nationalization generally; remote operations and the availability of
35



adequate infrastructure; fluctuations in price and availability of energy and other inputs necessary for mining operations; shortages or cost increases in necessary equipment, supplies and labour; regulatory, political and country risks, including local instability or acts of terrorism and the effects thereof; the reliance upon contractors, third parties and joint venture partners; the lack of sole decision-making authority related to Filminera Resources Corporation, which owns the Masbate Gold Project; challenges to title or surface rights; the dependence on key personnel and the ability to attract and retain skilled personnel; the risk of an uninsurable or uninsured loss; adverse climate and weather conditions; litigation risk; competition with other mining companies; community support for B2Gold's operations, including risks related to strikes and the halting of such operations from time to time; conflicts with small scale miners; failures of information systems or information security threats; the ability to maintain adequate internal controls over financial reporting as required by law, including Section 404 of the Sarbanes-Oxley Act; compliance with anti-corruption laws, and sanctions or other similar measures; social media and B2Gold's reputation; as well as other factors identified and as described in more detail under the heading "Risk Factors" in B2Gold's most recent Annual Information Form, B2Gold's current Form 40-F Annual Report and B2Gold's other filings with Canadian securities regulators and the U.S. Securities and Exchange Commission (the "SEC"), which may be viewed at www.sedarplus.ca and www.sec.gov, respectively (the "Websites"). The list is not exhaustive of the factors that may affect B2Gold's forward-looking statements.

B2Gold's forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. These assumptions and factors include, but are not limited to, assumptions and factors related to B2Gold's ability to carry on current and future operations, including: development and exploration activities; the timing, extent, duration and economic viability of such operations, including any mineral resources or reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments; B2Gold's ability to meet or achieve estimates, projections and forecasts; the availability and cost of inputs; the price and market for outputs, including gold; foreign exchange rates; taxation levels; the timely receipt of necessary approvals or permits; the ability to meet current and future obligations; the ability to obtain timely financing on reasonable terms when required; the current and future social, economic and political conditions; and other assumptions and factors generally associated with the mining industry.

B2Gold's forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date hereof. B2Gold does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur, or if any of them do, what benefits or liabilities B2Gold will derive therefrom. For the reasons set forth above, undue reliance should not be placed on forward-looking statements.

CAUTIONARY STATEMENT REGARDING MINERAL RESERVE AND RESOURCE ESTIMATES

The disclosure in this MD&A was prepared in accordance with Canadian National Instrument 43-101 (“NI 43-101”), which differs significantly from the requirements of the SEC, and resource and reserve information contained or referenced in this MD&A may not be comparable to similar information disclosed by public companies subject to the technical disclosure requirements of the SEC. Historical results or feasibility models presented herein are not guarantees or expectations of future performance.

QUALIFIED PERSONS

William Lytle, Senior Vice President and Chief Operating Officer, a qualified person under National Instrument 43-101, has reviewed and approved the disclosure of all scientific and technical information related to operational matters contained in this MD&A. Andrew Brown, P. Geo., Vice President, Exploration, a qualified person under NI 43-101, has approved the scientific and technical information regarding exploration matters contained in this MD&A.
36

Document
Form 52-109F2
Certification of Interim Filings
Full Certificate

I, Clive Johnson, President and Chief Executive Officer of B2Gold Corp., certify the following:

1.    Review: I have reviewed the interim financial report and interim MD&A (together, the “interim filings”) of B2Gold Corp. (the “issuer”) for the interim period ended June 30, 2024.

2.    No misrepresentations: Based on my knowledge, having exercised reasonable diligence, the interim filings do not contain any untrue statement of a material fact or omit to state a material fact required to be stated or that is necessary to make a statement not misleading in light of the circumstances under which it was made, with respect to the period covered by the interim filings.

3.    Fair presentation: Based on my knowledge, having exercised reasonable diligence, the interim financial report together with the other financial information included in the interim filings fairly present in all material respects the financial condition, financial performance and cash flows of the issuer, as of the date of and for the periods presented in the interim filings.

4.    Responsibility: The issuer’s other certifying officer(s) and I are responsible for establishing and maintaining disclosure controls and procedures (DC&P) and internal control over financial reporting (ICFR), as those terms are defined in National Instrument 52-109 Certification of Disclosure in Issuers’ Annual and Interim Filings, for the issuer.

5.    Design: Subject to the limitations, if any, described in paragraphs 5.2 and 5.3, the issuer’s other certifying officer(s) and I have, as at the end of the period covered by the interim filings

(a)    designed DC&P, or caused it to be designed under our supervision, to provide reasonable assurance that

(i)material information relating to the issuer is made known to us by others, particularly during the period in which the interim filings are being prepared; and

(i)information required to be disclosed by the issuer in its annual filings, interim filings or other reports filed or submitted by it under securities legislation is recorded, processed, summarized and reported within the time periods specified in securities legislation; and

(b)    designed ICFR, or caused it to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with the issuer’s GAAP.

5.1    Control framework: The control framework the issuer’s other certifying officer(s) and I used to design the issuer’s ICFR is the Internal Control-Integrated Framework published by The Committee of Sponsoring Organizations of the Treadway Commission.

5.2    ICFR – material weakness relating to design: N/A

5.3    Limitation on scope of design: N/A.

6.    Reporting changes in ICFR: The issuer has disclosed in its interim MD&A any change in the issuer’s ICFR that occurred during the period beginning on January 1, 2024 and ended on June 30, 2024 that has materially affected, or is reasonably likely to materially affect, the issuer’s ICFR.


Date: August 8, 2024

/s/ Clive Johnson 
Clive Johnson 
President and CEO 

Document
Form 52-109F2
Certification of Interim Filings
Full Certificate

I, Michael Cinnamond, Chief Financial Officer of B2Gold Corp., certify the following:

1.    Review: I have reviewed the interim financial report and interim MD&A (together, the “interim filings”) of B2Gold Corp. (the “issuer”) for the interim period ended June 30, 2024.

2.    No misrepresentations: Based on my knowledge, having exercised reasonable diligence, the interim filings do not contain any untrue statement of a material fact or omit to state a material fact required to be stated or that is necessary to make a statement not misleading in light of the circumstances under which it was made, with respect to the period covered by the interim filings.

3.    Fair presentation: Based on my knowledge, having exercised reasonable diligence, the interim financial report together with the other financial information included in the interim filings fairly present in all material respects the financial condition, financial performance and cash flows of the issuer, as of the date of and for the periods presented in the interim filings.

4.    Responsibility: The issuer’s other certifying officer(s) and I are responsible for establishing and maintaining disclosure controls and procedures (DC&P) and internal control over financial reporting (ICFR), as those terms are defined in National Instrument 52-109 Certification of Disclosure in Issuers’ Annual and Interim Filings, for the issuer.

5.    Design: Subject to the limitations, if any, described in paragraphs 5.2 and 5.3, the issuer’s other certifying officer(s) and I have, as at the end of the period covered by the interim filings

(a)    designed DC&P, or caused it to be designed under our supervision, to provide reasonable assurance that

(i)material information relating to the issuer is made known to us by others, particularly during the period in which the interim filings are being prepared; and

(i)information required to be disclosed by the issuer in its annual filings, interim filings or other reports filed or submitted by it under securities legislation is recorded, processed, summarized and reported within the time periods specified in securities legislation; and

(b)    designed ICFR, or caused it to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with the issuer’s GAAP.

5.1    Control framework: The control framework the issuer’s other certifying officer(s) and I used to design the issuer’s ICFR is the Internal Control-Integrated Framework published by The Committee of Sponsoring Organizations of the Treadway Commission.

5.2    ICFR – material weakness relating to design: N/A

5.3    Limitation on scope of design: N/A.

6.    Reporting changes in ICFR: The issuer has disclosed in its interim MD&A any change in the issuer’s ICFR that occurred during the period beginning on January 1, 2024 and ended on June 30, 2024 that has materially affected, or is reasonably likely to materially affect, the issuer’s ICFR.


Date: August 8, 2024
/s/ Michael Cinnamond 
Michael Cinnamond 
Chief Financial Officer